SAMPLEEarthing — electrodes, pits, strips, earth mat — this is what your report looks like, generated from demo inputs.Generate yours →2 free designs every day for every signed-in account · 1 design free on sign-in · ₹99 + GST per design (report + Excel + DXF) · free for DesignLink companies
Report ready — use Print → Save as PDF (A4 landscape).
calc.designlink.in
Earthing — electrodes, pits, strips, earth mat
Sample project — Tower A · Electrical
Generated 28 Nov 2026 16:09 Single electrode resistance (pipe / rod / plate / strip), electrodes in parallel to reach … Project code SAMPLE
Soil resistivity governs everything — use a measured value (IS 3043 cl. 8, Wenner method) and the wet-season value for design; record it where a transformer is in the facility (NBCS 8.2.11).
Combined resistance of electrodes uses the IS 3043 Table 12 λ factors (rods in a line / hollow square); mutual effects make many close electrodes inefficient.
All earthing systems of the building (power, LPS, IT / UPS, telecom) are interconnected at ground level (NBCS 8.2.20); isolated earthing is unsafe during transients — where unavoidable use earth couplers / isolating spark gaps (8.2.24).
Soil treatment: earth-enhancing compound per NBCS 8.4; common salt (NaCl) is not used — it accelerates corrosion of ferrous electrodes (8.4.4). Alternative per 8.3: 50 mm GI strip with 100 mm CI pipe.
NBCS 2026 sets no general resistance value for power earthing — the target is project practice (≤ 1 Ω substations, ≤ 5 Ω LT); the LPS earth should be < 10 Ω (11.6.3).
Earth mat formulas per IEEE 80-2013 (Sverak R_g, Km/Ki/Ks mesh and step); verify with a soil model and fault current from the utility.
6. Standards and references
IS 3043:2018 — Code of practice for earthing: Earth bus, strip sizing, earthing of panels (future earthing tool)
CEA (Measures relating to Safety and Electric Supply) Regulations, 2023 — Central Electricity Authority safety regulations: Statutory safety requirements for installations
IEEE Std 80-2013 — Guide for Safety in AC Substation Grounding: Earth grid resistance, touch and step voltages
NBCS 2026 (SP 7:2026) Part D Sec 2 — National Building Construction Standards — Electrical and allied installations: Load assessment and diversity, circuits, cables (4-core), earthing, lightning protection, standby supply for fire & life-safety loads
Prepared by
Checked by
Approved by
Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.