SAMPLE Electrical layouts — lighting circuits, DB diagrams, cable tray — this is what your report looks like, generated from demo inputs. Generate yours → 2 free designs every day for every signed-in account · 1 design free on sign-in · ₹99 + GST per design (report + Excel + DXF) · free for DesignLink companies
Report ready — use Print → Save as PDF (A4 landscape).
Design Linkcalc.designlink.in

Electrical layouts

Sample project — Tower A · Lighting circuits & wiring on the plan · DB wiring diagrams · cable-tray plan
Generated 28 Nov 2026 16:09
From the lighting model and the feeder schedule
Project code SAMPLE
Floors
1
Luminaires
43
Circuits
6
Connected
1401 W
Wire
787.8 m
Conduit
227.8 m

1. Lighting circuits — basis

ItemValue
RegimeIndian — NBCS 2026 (SP 7:2026) Part D Sec 2
Circuit limits800 W / 10 points per circuit (CPWD General Specifications for Electrical Works Part I; NBCS 2026 cl. 5.4.4.3 allows a dedicated lighting circuit 800 W or 20 points, so the 10-point packing is the stricter)
MCBIn ≥ Ib, 6 A up to 500 W, 10 A above — the same rule as the load estimate and the CAD circuits (NBCS 6.2: breaker matched to the circuit)
Wiring1.5 mm² FRLS Cu in MS conduit, loop-in from the room switch
Emergency luminairesseparate circuits — NBCS Part F 3.5.6.1: source independent of the normal lighting (DG-backed), on within 5 s, ≥ 90 min, battery packs not in lieu of the DG
PhasesR-Y-B balanced on TPN DBs (largest circuit first)
Switchesat the room entrance nearest the DB
Common areasown circuits — NBCS 5.4.4.4 (corridors, lobbies, stairs …); 3-wire individual + master control near the entrance of large halls
Window (daylight) zonenot split — set a window-zone width to group them — NBCS 5.4.4.5 / 5.4.4.6
Voltage dropVD basis: split: 6 % to the final DB + 3 % final circuit — NBCS 2026 (SP 7:2026) Part D Sec 2 cl. 6.2 / 5.6 Note a; final-circuit limit per DB below (LDB-Ground ≤ 3 %): whole circuit current over the longest path, 2-core Cu mV/A/m — conservative

2. Ground — LDB-Ground

Corridor · 7 × LED downlight 15 W · L1, L2Office 2 · 8 × LED panel 600×600 36 W · L3, L4Open office · 20 × LED panel 600×600 36 W · L3, L4, L5, L6Office 1 · 8 × LED panel 600×600 36 W · L4, L6L1L1L1L1L1L1L2EL3L3L3L3L3L3L3L3L3L3L4EL4EL4EL4EL4EL4EL4EL4EL4EL5L5L5L5L5L5L5L5L5L5L6L6L6L6L6L6L6SSSSLDB-Ground · 8-way · 1401 WGround: 43 luminaires · 6 circuits · 1401 W · R Y B
CircuitPhaseDescriptionPointsWIb AMCBWireWiring mVD path mVD %Limit %VD check
L1RLighting — Corridor6900.436 A1.5 mm²31.031.30.173.0PASS
L2YEmergency lighting — Corridor1150.076 A1.5 mm²15.215.50.013.0PASS
L3RLighting — Office 2, Open office103601.746 A1.5 mm²42.129.20.643.0PASS
L4BEmergency lighting — Office 2, Open office, Office 193241.576 A1.5 mm²54.849.90.983.0PASS
L5YLighting — Open office103601.746 A1.5 mm²53.965.81.443.0PASS
L6BLighting — Open office, Office 172521.226 A1.5 mm²35.043.80.673.0PASS

Final-circuit VD limit 3 % — DB → last point ≤ 3 % (split basis: the DB itself ≤ 6 % from the transformer) (NBCS 2026 (SP 7:2026) Part D Sec 2 cl. 6.2 / 5.6 Note a).

DBWaysTypeConnectedIbIncomerRCCBR / Y / B W
LDB-Ground8TPN1401 W2.2 A32 A40 A 30 mA450 / 375 / 576

3. Lighting checks

CheckResult
Every lighting circuit ≤ 800 W and ≤ 10 points (CPWD packing; NBCS 2026 cl. 5.4.4.3 allows a dedicated lighting circuit 800 W or 20 points — stricter here)PASS
Emergency luminaires on separate circuits, fed from a source independent of the normal lighting (DG-backed emergency supply), on within 5 s, ≥ 90 min; battery packs not in lieu of the DG — NBCS Part F 3.5.6.1 (b, f, g)PASS
Phase unbalance ≤ 20 % on every TPN DBPASS
LDB-Ground: final-circuit voltage drop ≤ 3 % — DB → last point ≤ 3 % (split basis: the DB itself ≤ 6 % from the transformer) (NBCS 2026 (SP 7:2026) Part D Sec 2 cl. 6.2 / 5.6 Note a) — worst L5 1.44 % over 65.8 mPASS
Common-area lighting (corridors, lobbies, stairs) on separate circuits — NBCS 2026 cl. 5.4.4.4PASS

4. Cable tray plan

Cables routed
1 / 1
Tray
39.5 m
Widest
100 mm
T1 CT 100×50 · 1 cables · fill 22 %CT 100×50 · 1c · 22%T2 CT 100×50 · 1 cables · fill 22 %CT 100×50 · 1c · 22%MAIN LT PANELLDB-GFCable tray plan: 1/1 cables routed · 39.5 m of tray · max 100 mm
SegmentLength mCablesRunsNeed mmTrayFill %SupportsCables
T111.51153CT 100×50228F1
T228.01153CT 100×502219F1
CableFromToSizeRunsOD mmTray length mTotal mRouted
F1MAIN LT PANELLDB-GF4C X 16 Sq.mm, Cu122.039.546.5PASS

Sizing: single layer, fill ≤ 50 % of the width (IEC 61537 / NEMA VE 2 practice), 20 % spare, standard widths; depth from the largest cable; supports every 1.5 m.

5. Tray checks

CheckResult
Fill ≤ 50 % of the tray width (single layer) on every segmentPASS
Every cable routed on the tray networkPASS
No more than 3 tiersPASS

6. Bill of quantities

ItemQtyUnit
Luminaire — LED downlight 15 W (15 W)7nos
Luminaire — LED panel 600×600 36 W (36 W)36nos
Wire 1.5 mm² FRLS Cu (P+N+E)787.8m
MS conduit227.8m
Switch boards4nos
DB — 8-way TPN DB, 32 A incomer + 40 A RCCB1nos
Perforated tray 100 × 50 mm HDG39.5m
Supports / hangers27nos

7. Worked examples — from this project

Worked from this project’s own inputs and results — each value can be traced to the schedules above.

Circuit LDB-Ground / L3 — Lighting — Office 2, Open office
the most loaded lighting circuit of the project
Given: Luminaires 10 nos at 36 W · Rule ≤ 800 W and ≤ 10 points per circuit (Indian regime) · Supply 230 V 1φ, pf 0.9
1. Circuit load: P = Σ luminaire watts = 10 × 36 = 360 W
2. Watts: P ≤ 800 W → 360 W PASS
3. Points: n ≤ 10 → 10 PASS
4. Design current: Ib = P / (230 · cosφ) = 360 / (230 · 0.9) = 1.74 A
5. MCB: next standard rating ≥ max(Ib, 6 A) = 1.74 A = 6 A SP (10 A minimum above 500 W — same rule as the load estimate and the CAD circuits)
6. Wire: 1.5 mm² Cu for a 6 A MCB → 1.5 mm² PASS
7. Wiring length: Σ (loop-in chain from the switch × 1.15 + 0.6 m per luminaire) = 42.1 m (2 room(s), nearest-neighbour chain on the plan; × 3 for phase + neutral + earth in the BOQ)
8. Voltage drop to the last point: ΔU = mV/A/m · Ib · L / 1000; ΔU % = ΔU / 230 = 29 · 1.74 · 29.2 / 1000 = 1.47 V = 0.64 % (L = home run + loop of the farthest room; whole current at the end (conservative))
9. Final-circuit VD: ΔU ≤ 3 % (NBCS 2026 (SP 7:2026) Part D Sec 2 cl. 6.2 / 5.6 Note a, split basis) → 0.64 % PASS
DB LDB-Ground — Ground
6 lighting circuits on this board
1. Connected load: P = Σ circuit watts = 90 + 15 + 360 + 324 + 360 + 252 = 1401 W
2. Design current: Ib = P / (√3 · U · cosφ) = 1401 / (1.732 · 415 · 0.9) = 2.2 A (engine 2.2 A)
3. Incomer: next standard rating ≥ max(1.25 · Ib, 32 A) = 1.25 × 2.2 = 2.8 A = 32 A (RCCB 40 A 30 mA)
4. Ways: next standard DB ≥ 1.2 × circuits = 1.2 × 6 = 7.2 = 8 (4, 6, 8, 12, 16, 18, 24, 36-way (TPN: ways per phase row))
5. Phase balance: max − min ≤ 20 % of the total → R 450 · Y 375 · B 576 W → 201 ≤ 280 W PASS
Tray segment T2 — 28.0 m, 1 cable(s)
the most heavily loaded tray segment
Given: Cables F1 4C X 16 Sq.mm, Cu × 1 (OD 22 mm)
OD from the cable text by the typical armoured XLPE diameter table (IS 7098-1 typical values) unless given.
1. Required width: w = Σ(OD · runs) · (1 + spacing) · (1 + spare) / fill = 22 · 1 · 1.2 / 0.5 = 53 mm
2. Tray chosen: next standard width ≥ w / tiers = from 50, 100, 150, 200, 300, 450, 600, 750, 900 = CT 100×50 (depth ≥ 1.2 × largest OD, min 50 mm)
3. Fill: Σ(OD · runs) / (width · tiers) ≤ 50 % → 22 / (100 × 1) = 22 % PASS
4. Supports: n = ⌈L / spacing⌉ = ⌈28.0 / 1.5⌉ = 19 nos

8. Standards applied

StandardUsed for
NBCS 2026 (SP 7:2026) Part D Sec 2cl. 5.4.4.3 circuit limits, 5.4.4.4 common-area circuits, 5.4.4.5 / 5.4.4.6 window-zone controls, 6.2 / 5.6 Note a voltage drop (6 % to the final DB, 3 % DB → last point — split or total basis)
NBCS 2026 Part Fcl. 3.5.6.1 escape lighting — independent source, 5 s, 90 min
CPWD General Specifications for Electrical Works Part I (Internal) 2023Points per circuit, 800 W limit, wiring, conduits, DBs
IS 732:2019Code of practice for electrical wiring installations
IS 7098 / IS 1554Cable dimensions
IEC 61537Cable tray and ladder systems
Prepared by
Checked by
Approved by

Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.