| Criterion | Value | Reference |
|---|---|---|
| Standard | India — NBCS 2026 (SP 7:2026) Part F · IS 15105:2021 · IS 3844:1989 · IS 13039:2014 · TAC | |
| Code edition | NBCS 2026 (SP 7:2026) Part F (default; NBC 2016 Part 4 selectable) | SP 7:2026 Part F |
| Sprinkler hazard classes | Light hazard (LH): 2.25 mm/min over 84 m², K 57, ≥ 0.7 bar, hose 0 L/min, 30 min Ordinary hazard (OH): 5.0 mm/min over 360 m², K 80, ≥ 0.5 bar, hose 0 L/min, 60 min Ordinary hazard (OH) — was OH-II in IS 15105:2002: 5.0 mm/min over 360 m², K 80, ≥ 0.5 bar, hose 0 L/min, 60 min Ordinary hazard (OH) — was OH-III in IS 15105:2002: 5.0 mm/min over 360 m², K 80, ≥ 0.5 bar, hose 0 L/min, 60 min Ordinary hazard (OH) — was OH-III special in IS 15105:2002: 5.0 mm/min over 360 m², K 80, ≥ 0.5 bar, hose 0 L/min, 60 min High hazard (HH) process: 12.2 mm/min over 260 m², K 115, ≥ 0.5 bar, hose 0 L/min, 120 min High hazard (HH) — was EHP-II in IS 15105:2002: 12.2 mm/min over 260 m², K 115, ≥ 0.5 bar, hose 0 L/min, 120 min High hazard (HH) — was EHP-III in IS 15105:2002: 12.2 mm/min over 260 m², K 115, ≥ 0.5 bar, hose 0 L/min, 120 min | IS 15105:2021 cl. 8.1.1 (2.25 L/min/m² over 84 m²), 9.17 (21 m²/head, 4.5 m), 10.5.7 (≥ 0.7 bar), Table 1 (K57/80), Table 30 (30 min) IS 15105:2021 cl. 8.1.2 (5 L/min/m² over 360 m² — one OH class), 9.17 (12 m²/head, 4.5 m), 10.5.7 (≥ 0.5 bar), Table 1 (K80/115), Table 30 (60 min) IS 15105:2021 cl. 8.1.2 (5 L/min/m² over 360 m² — one OH class), 9.17 (12 m²/head, 4.5 m), 10.5.7 (≥ 0.5 bar), Table 1 (K80/115), Table 30 (60 min) IS 15105:2021 cl. 8.1.2 (5 L/min/m² over 360 m² — one OH class), 9.17 (12 m²/head, 4.5 m), 10.5.7 (≥ 0.5 bar), Table 1 (K80/115), Table 30 (60 min) IS 15105:2021 cl. 8.1.2 (5 L/min/m² over 360 m² — one OH class), 9.17 (12 m²/head, 4.5 m), 10.5.7 (≥ 0.5 bar), Table 1 (K80/115), Table 30 (60 min) IS 15105:2021 cl. 8.1.3 (12.2 L/min/m² over 260 m² — one HH process class), 9.17 (9 m²/head, 3.75 m), 10.5.7 (≥ 0.5 bar), Table 1 (K115/160), Table 30 (120 min); fully calculated per 10.3.2 IS 15105:2021 cl. 8.1.3 (12.2 L/min/m² over 260 m² — one HH process class), 9.17 (9 m²/head, 3.75 m), 10.5.7 (≥ 0.5 bar), Table 1 (K115/160), Table 30 (120 min); fully calculated per 10.3.2 IS 15105:2021 cl. 8.1.3 (12.2 L/min/m² over 260 m² — one HH process class), 9.17 (9 m²/head, 3.75 m), 10.5.7 (≥ 0.5 bar), Table 1 (K115/160), Table 30 (120 min); fully calculated per 10.3.2 |
| Wet riser / standpipe | 1800 L/min; 3.5 bar at the topmost outlet; ≤ 7.0 bar at any outlet; main size by occupancy and height per NBCS 2026 Table 8 (100 mm / 150 mm) | IS 3844 — two landing valves (2 × 900 L/min) operating on the topmost floor (wet riser per NBCS 2026 Part F Tables 7A–7J) · NBCS 2026 Part F cl. 5.1.1 (f) — ≥ 3.5 bar at the hydraulically remote and the highest hydrant · NBCS 2026 Part F cl. 5.1.1 (f) — ≤ 7.0 bar at any hydrant; orifice plates / pressure-controlled landing valves at lower levels · NBCS 2026 Part F cl. 5.1.1 (a) Table 8 — 100 mm or 150 mm main by occupancy and height (150 mm above 15 m for most rows) |
| External hydrants | 1800 L/min per hydrant, 2 operating; ≥ 3.5 bar residual; spacing ≤ 45 m; ring ≥ 100 mm | IS 13039 — double-headed hydrant 2 × 900 L/min; two hydrants operating simultaneously (light / ordinary hazard) · NBCS 2026 Part F cl. 5.1.1 (f) / IS 13039 — ≥ 3.5 bar at the hydraulically remote hydrant · IS 13039 cl. 5 — hydrants ≤ 45 m apart (30 m high hazard), 2–15 m from the building |
| Velocity | ≤ 6.0 m/s sprinkler / riser; ≤ 5.0 m/s ring main | typical practice (TAC) — ≤ 6 m/s in risers |
| Head loss | Hazen-Williams · ring main DI · risers / sprinkler pipes MS; fittings 20 % of pipe length | fittings allowance 20 % of pipe length (typical) unless counted per pipe |
| Fire pump | 150 % flow at ≥ 65 % head; shut-off ≤ 140 %; diesel standby 100 %; jockey 180 L/min | NBCS 2026 Part F Tables 7A–7J (level of protection) → Table 7K / 7M pump and storage when the occupancy is given; IS 12469 pumps: 150 % flow at ≥ 65 % head, shut-off ≤ 140 %; shut-off ≤ 12 bar for buildings above 60 m |
| Water tank | max(calculated duration × demand, code table) | NBCS 2026 Part F Table 7K / 7M — level demand × duration (30–120 min, Note 2) — or scenario demand × duration where larger |
| Pump shut-off / sprinkler system | pump shut-off ≤ 12 bar for buildings above 60 m; sprinkler system ≤ 12 bar (else high-pressure sprinklers) | NBCS 2026 Part F Table 7A Note 5 / 7B Note 5 / 7C Note 3 / 7E Note 4 · cl. 5.1.3 (f) |
| Building | Hazard | Floors / height | Ring node | Sprinkler design area (most remote) | Wet riser / standpipe |
|---|---|---|---|---|---|
| Tower A | Ordinary hazard (OH) | 12 / 38.4 m | N3 | 30 heads (5 × 7) · 360 m² · 5.00 mm/min · K80 demand 2,723 + hose 0 = 2,723 L/min at 8.73 bar (89.1 m) at the connection · remote head 0.65 bar, 60.0 L/min · density achieved 5.00 mm/min · V max 5.8 m/s · tank 163.4 kL (60 min) | 2 riser(s) 150.0 mm · 1,800 L/min (system 1,800) · V 1.70 m/s · h_f 1.36 m required at connection 7.40 bar (75.5 m) for 3.5 bar at the top outlet PRV / orifice at landing valves on floors 1, 2 (> 7.0 bar) Table 8: ii) above 15 m (no occupancy given — most rows) → 150 mm |
| Office | Light hazard (LH) | 4 / 14.4 m | N2 | 5 heads (2 × 3) · 84 m² · 2.25 mm/min · K57 demand 266 + hose 0 = 266 L/min at 2.71 bar (27.6 m) at the connection · remote head 0.70 bar, 47.7 L/min · density achieved 2.36 mm/min · V max 3.7 m/s · tank 8.0 kL (30 min) | 1 riser(s) 100.0 mm · 1,800 L/min (system 1,800) · V 3.82 m/s · h_f 4.94 m required at connection 5.40 bar (55.0 m) for 3.5 bar at the top outlet Table 8: i) up to 15 m (no occupancy given — most rows) → 100 mm |
Riser pressure vs floor: running pressure at each landing valve with the riser at its design flow; band 3.5–7 bar (NBCS 2026 Part F cl. 5.1.1 (f) — ≤ 7.0 bar at any hydrant; orifice plates / pressure-controlled landing valves at lower levels). Static (no-flow) pressures at pump shut-off are higher — set the orifice / PRV on that basis.
| Node | Elev (m) | K | q head L/min | Q L/min | P_t bar | Pipe | Size | ID mm | L m | Fittings | L_eq m | L_tot m | C | V m/s | p_f bar/m | P_f bar | P_e bar | P_next bar |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| H1-7 | 38.40 | 80.0 | 64.2 | 64.2 | 0.645 | B1-7 | 25 | 25.0 | 3.46 | — | 0.00 | 3.46 | 120.0 | 2.18 | 0.0295 | 0.102 | 0.000 | 0.747 |
| H1-6 | 38.40 | 80.0 | 69.1 | 133.4 | 0.747 | B1-6 | 25 | 25.0 | 3.46 | — | 0.00 | 3.46 | 120.0 | 4.53 | 0.1141 | 0.395 | 0.000 | 1.142 |
| H1-5 | 38.40 | 80.0 | 85.5 | 218.9 | 1.142 | B1-5 | 32 | 32.0 | 3.46 | — | 0.00 | 3.46 | 120.0 | 4.54 | 0.0859 | 0.297 | 0.000 | 1.440 |
| H1-4 | 38.40 | 80.0 | 96.0 | 314.8 | 1.440 | B1-4 | 40 | 40.0 | 3.46 | — | 0.00 | 3.46 | 120.0 | 4.18 | 0.0568 | 0.197 | 0.000 | 1.636 |
| H1-3 | 38.40 | 80.0 | 102.3 | 417.2 | 1.636 | B1-3 | 40 | 40.0 | 3.46 | — | 0.00 | 3.46 | 120.0 | 5.53 | 0.0957 | 0.331 | 0.000 | 1.968 |
| H1-2 | 38.40 | 80.0 | 112.2 | 529.4 | 1.968 | B1-2 | 50 | 50.0 | 3.46 | — | 0.00 | 3.46 | 120.0 | 4.49 | 0.0502 | 0.174 | 0.000 | 2.141 |
| H1-1 | 38.40 | 80.0 | 117.1 | 646.5 | 2.141 | B1-1 | 50 | 50.0 | 1.73 | 1×tee | 3.10 | 4.83 | 120.0 | 5.49 | 0.0726 | 0.351 | 0.000 | 2.492 |
| CM1 | 38.40 | 2,722.7 | 2.492 | X1 | 100 | 100.0 | 1.73 | 1×tee | 6.10 | 7.83 | 120.0 | 5.78 | 0.0356 | 0.279 | 0.000 | 2.771 | ||
| RT | 38.40 | 2,722.7 | 2.771 | FEED | 100.0 | 100.0 | 48.40 | 2×ell90, 1×gate, 1×check | 13.30 | 61.70 | 120.0 | 5.78 | 0.0356 | 2.197 | 3.766 | 8.734 | ||
| CONN | 0.00 | 2,722.7 | 8.734 | — |
P_next = P_t + P_f + P_e (P_e positive when moving down toward the source). Branch lines not on the remote path carry balanced flows solved simultaneously (head-to-head balancing); all 30 head flows: H1-1 117 L/min @ 2.14 bar, H1-2 112 L/min @ 1.97 bar, H1-3 102 L/min @ 1.64 bar, H1-4 96 L/min @ 1.44 bar, H1-5 86 L/min @ 1.14 bar, H1-6 69 L/min @ 0.75 bar, H1-7 64 L/min @ 0.65 bar, H2-1 115 L/min @ 2.08 bar, H2-2 110 L/min @ 1.91 bar, H2-3 101 L/min @ 1.59 bar, H2-4 94 L/min @ 1.40 bar, H2-5 84 L/min @ 1.11 bar, H2-6 68 L/min @ 0.72 bar, H2-7 63 L/min @ 0.62 bar, H3-1 113 L/min @ 1.98 bar, H3-2 108 L/min @ 1.82 bar, H3-3 98 L/min @ 1.51 bar, H3-4 92 L/min @ 1.33 bar, H3-5 82 L/min @ 1.05 bar, H3-6 66 L/min @ 0.69 bar, H3-7 62 L/min @ 0.59 bar, H4-1 110 L/min @ 1.89 bar, H4-2 105 L/min @ 1.73 bar, H4-3 96 L/min @ 1.44 bar, H4-4 90 L/min @ 1.26 bar, H4-5 80 L/min @ 1.00 bar, H4-6 65 L/min @ 0.65 bar, H4-7 60 L/min @ 0.56 bar, H5-1 110 L/min @ 1.90 bar, H5-2 103 L/min @ 1.65 bar.
| Node | Elev (m) | K | q head L/min | Q L/min | P_t bar | Pipe | Size | ID mm | L m | Fittings | L_eq m | L_tot m | C | V m/s | p_f bar/m | P_f bar | P_e bar | P_next bar |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| H1-3 | 14.40 | 57.0 | 47.7 | 47.7 | 0.700 | B1-3 | 25 | 25.0 | 4.50 | — | 0.00 | 4.50 | 120.0 | 1.62 | 0.0170 | 0.076 | 0.000 | 0.777 |
| H1-2 | 14.40 | 57.0 | 50.2 | 97.9 | 0.777 | B1-2 | 25 | 25.0 | 4.50 | — | 0.00 | 4.50 | 120.0 | 3.32 | 0.0644 | 0.290 | 0.000 | 1.066 |
| H1-1 | 14.40 | 57.0 | 58.9 | 156.8 | 1.066 | B1-1 | 32 | 32.0 | 2.25 | 1×tee | 1.80 | 4.05 | 120.0 | 3.25 | 0.0463 | 0.187 | 0.000 | 1.254 |
| CM1 | 14.40 | 265.5 | 1.254 | X1 | 65 | 65.0 | 2.25 | 1×tee | 3.70 | 5.95 | 120.0 | 1.33 | 0.0039 | 0.023 | 0.000 | 1.277 | ||
| RT | 14.40 | 265.5 | 1.277 | FEED | 100.0 | 100.0 | 24.40 | 2×ell90, 1×gate, 1×check | 13.30 | 37.70 | 120.0 | 0.56 | 0.0005 | 0.018 | 1.412 | 2.707 | ||
| CONN | 0.00 | 265.5 | 2.707 | — |
P_next = P_t + P_f + P_e (P_e positive when moving down toward the source). Branch lines not on the remote path carry balanced flows solved simultaneously (head-to-head balancing); all 5 head flows: H1-1 59 L/min @ 1.07 bar, H1-2 50 L/min @ 0.78 bar, H1-3 48 L/min @ 0.70 bar, H2-1 56 L/min @ 0.96 bar, H2-2 53 L/min @ 0.86 bar.
| Scenario | Flow (L/min) | Head required at pump (m) | Head available from pump (m) | Duration (min) | Tank (kL) | Status |
|---|---|---|---|---|---|---|
| Sprinkler design area + hose — Tower A (Ordinary hazard (OH)) | 2,723 | 117.8 | 129.6 | 60 | 163.4 | PASS |
| Wet riser / standpipe — Tower A (1800 L/min, 3.5 bar at the top outlet) | 1,800 | 92.6 | 137.2 | 30 | 54.0 | PASS |
| External hydrants — 2 × 1800 L/min at the farthest hydrants (N3, N2), ≥ 3.5 bar | 3,600 | 68.1 | 117.8 | 60 | 216.0 | PASS |
| Item | Value |
|---|---|
| Main fire pump (electric) | 3,600 L/min (216.0 m³/h) @ 117.8 m (11.55 bar) — governing: sprinkler |
| Standby diesel pump | 100 % — 3600 L/min @ 118 m |
| Jockey pump | 180 L/min @ 130 m |
| Terrace / booster pump | — |
| Suction water level | 97.00 m |
| Power (hydraulic / shaft η 70 %) | 69.3 / 99.1 kW |
| Curve envelope | shut-off 141.4 m = 13.9 bar (120 % PASS) · 150 % flow at 76.6 m (65 % PASS) |
| Scenario | Flow (L/min) | Duration (min) | Volume (kL) |
|---|---|---|---|
| Sprinkler design area + hose — Tower A (Ordinary hazard (OH)) | 2,723 | 60 | 163.4 |
| Wet riser / standpipe — Tower A (1800 L/min, 3.5 bar at the top outlet) | 1,800 | 30 | 54.0 |
| External hydrants — 2 × 1800 L/min at the farthest hydrants (N3, N2), ≥ 3.5 bar | 3,600 | 60 | 216.0 |
| Code table (none applied) | 0.0 | ||
| Adopt | 216.0 kL |
| Check | Result | Note |
|---|---|---|
| Yard hydrants ≤ 7 bar running pressure (NBCS 2026 Part F cl. 5.1.1 (f)) | ACTION | orifice plate / pressure-controlled hydrant valve at N2, N3, N4 |
| Tower A: landing valves ≤ 7 bar (NBCS 2026 Part F cl. 5.1.1 (f)) | ACTION | orifice plates / PRVs on floors 1, 2 |
| Tower A: riser 150 mm ≥ NBCS 2026 Table 8 size 150 mm — row ii) above 15 m (no occupancy given — most rows) | PASS | |
| Office: landing valves ≤ 7 bar (NBCS 2026 Part F cl. 5.1.1 (f)) | PASS | |
| Office: riser 100 mm ≥ NBCS 2026 Table 8 size 100 mm — row i) up to 15 m (no occupancy given — most rows) | PASS | |
| Sprinkler system pressure ≤ 12 bar (NBCS 2026 Part F cl. 5.1.3 (f)) | ACTION | pump shut-off 13.9 bar — high-pressure sprinklers or zone PRVs at the installation control valves |
| Node | Type | GL (m) | Min pressure (m / bar) | Required (m) | Status | sprinkler (bar) | riser (bar) | hydrant (bar) |
|---|---|---|---|---|---|---|---|---|
| N1 | pump | 100.00 | 65.1 / 6.39 | — | PASS | 11.26 | 8.79 | 6.39 |
| N2 | hydrant | 100.50 | 39.9 / 3.92 | 35.7 | PASS > 7 bar: orifice | 10.15 | 8.24 | 3.92 |
| N3 | hydrant | 101.00 | 38.7 / 3.79 | 89.1 | PASS > 7 bar: orifice | 9.03 | 7.69 | 3.79 |
| N4 | hydrant | 100.80 | 51.6 / 5.06 | — | PASS > 7 bar: orifice | 10.12 | 8.21 | 5.06 |
| Pipe | L (m) | Size (mm) | ID (mm) | Material | C | Q max (L/min) | V max (m/s) | h_f (m) | Status |
|---|---|---|---|---|---|---|---|---|---|
| N1 → N2 | 120.0 | 100 | 100.0 | DI | 140 | 2,119 | 4.50 | 24.70 | PASS |
| N2 → N3 | 120.0 | 100 | 100.0 | DI | 140 | 1,362 | 2.89 | 10.89 | PASS |
| N3 → N4 | 120.0 | 100 | 100.0 | DI | 140 | 1,481 | 3.14 | 12.72 | PASS |
| N4 → N1 | 120.0 | 100 | 100.0 | DI | 140 | 1,481 | 3.14 | 12.72 | PASS |
Worked from this project’s own inputs and results — the values can be traced to the calculation sheets and tables above.
| Material | Size (mm) | Length (m) |
|---|---|---|
| DI | 100 | 480.0 |
| Quantity | Formula | Reference |
|---|---|---|
| Sprinkler discharge | Q (L/min) = K · √P (bar) | NFPA 13 cl. 27.2.2.2 / IS 15105 cl. 11 |
| Minimum head flow | q_head = max( density × area per head , K·√P_min ) | NFPA 13 cl. 27.2.4.1 / IS 15105 |
| Design area & heads | n = ⌈A_design / A_head⌉ ; heads per branch = ⌈1.2·√A_design / S_head⌉ | NFPA 13 cl. 27.2.4.3 (1.2·√A rule) |
| Hazen-Williams | h_f = 10.67·L·Q^1.852 / (C^1.852·D^4.87) (SI) ≡ p = 6.05·Q^1.85·10⁵ / (C^1.85·d^4.87) bar/m | NFPA 13 cl. 27.2.2.1 / IS 15105 cl. 11.4 |
| Fittings | L_eq from the equivalent-length table (C = 120), × (120/C)^1.85 | NFPA 13 Table 28.2.3.1.2 |
| Elevation | P_e = 0.098 bar per metre | NFPA 13 cl. 27.2.2.4 |
| Network solution | Global gradient algorithm with sprinkler heads as emitters Q = K·√P (implicit head-to-head balancing) | Todini & Pilati 1988 (EPANET) — equivalent to NFPA 13 ch. 27 step-by-step balancing |
| Standpipe / wet riser demand | Q = Q_first + Q_add × (n − 1) ≤ Q_max ; P_base = P_top + 0.098·H + h_f(riser + fittings) | NFPA 14 cl. 7.10 / IS 3844 |
| Pump demand | Q_pump = max(sprinkler + hose, riser/standpipe, hydrant × n_sim, code table) ; H_pump = max over scenarios of head required at the pump | NFPA 20 cl. 4.8 / NBCS 2026 Part F Table 7K / 7M |
| Pump curve check | H(0) ≤ 140 % H_rated ; H(150 % Q) ≥ 65 % H_rated | NFPA 20 cl. 6.2 / IS 12469 |
| Tank | V = max( (Q_sprinkler + Q_hose) × t_duration , Q_riser × t_riser , code table ) | NFPA 22 / NFPA 13 Table 19.2.3.1.2 / NBCS 2026 Part F Table 7K / 7M |
Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.