SAMPLE Load estimation & DB schedules — this is what your report looks like, generated from demo inputs. Generate yours → 2 free designs every day for every signed-in account · 1 design free on sign-in · ₹99 + GST per design (report + Excel + DXF) · free for DesignLink companies
Report ready — use Print → Save as PDF (A4 landscape).
Design Linkcalc.designlink.in

Electrical load estimation & DB schedules

Sample project — Tower A · Indian regime · NBCS 2026 · 6 rooms · 2 boards
Generated 28 Nov 2026 16:09
Rooms → circuits → boards → panels → feeders
Project code SAMPLE
Rooms
6
Area
534.0 m²
Connected
98.3 kW
Demand (main)
114.6 kW · 127.3 kVA
Transformer
160 kVA
DBs / circuits
2 / 73
Max unbalance
1.1 %

1. Design basis

ItemValueSource
Code regimeIndian — NBCS 2026 (SP 7:2026) Part D Sec 2 · IS 732 · CPWD General Specifications (Electrical) Part I · ECSBC 2024project
Code editionNBCS 2026 (SP 7:2026) Part D Sec 2 — defaultproject
Type of building (diversity column)Small shops, stores, offices and business premisesNBCS 4.2.2.2
Lighting densityECSBC 2024 cl. 7.3.3, Tables 7.4 / 7.5 / 7.6 (space function LPD, PDF p. 92–96 — the energy-code tool's table) — per room type, W/m²energy code
Small powerroom-type raw-power VA/m² (CPWD practice) or the socket points (6 A = 100 W, 16 A = 1000 W), whichever is higher; building check against NBCS 5.9.2 (≥ 55 W/m²) in section 5code / practice
Air-conditioningsplit units 1500 W each from the room's W/m²; central HVAC = AHU / FCU share per room, plant as an extra load on the HVAC panelproject
Demand factorsLighting 90 % (4.2.2.2 Sl i); Small power 50 % (cl. 5.9.2); Equipment 100 % largest + 75 % rest (4.2.2.2 Sl ii / xiv); Central AC low side 90 % (4.2.2.2 Sl iv low side); Central AC plant 80 % (4.2.2.2 Sl iv high side); Cooking 100 % largest + 80 % second + 60 % rest (4.2.2.2 Sl v); Motors / pumps 100 % largest + 80 % second + 60 % rest (4.2.2.2 Sl vii); Lifts 100 % (4.2.2.2 Sl viii); Split AC 100 % up to 200 m², 85 % beyond (Sl iii) · sub-panel 0.9 · main 0.85 (overall load factor within the 50–90 % of the note to NBCS 4.2.2.2)NBCS 2026 Part D Sec 2 cl. 4.2.2.2 diversity table (by type of building) and cl. 5.9.2 (power ≤ 50 %)
Circuit rulesNBCS 2026 Part D Sec 2 cl. 5.4.4.3: mixed circuit (lights, fans, 6 A sockets) ≤ 10 points and 800 W, dedicated lighting ≤ 20 points / 800 W, 6 A socket circuit ≤ 8 nos / 800 W, fans ≤ 10, 16 A outlets ≤ 2 per circuit on 4 mm² Cu; cl. 5.4.4.7 sub-circuit ≤ 3 000 W · CPWD General Specifications Part I: separate circuit per ACwiring code
System415 V, pf 0.9, boards combined LPDB per floor and zone, floor panelsproject

2. Room-wise connected load

FloorRoomTypem²Light WLight pts6 A16 APower WACAC WHVAC WEquipment WTotal WW/m²Board
GFReceptionReception / waiting40.036411211200split × 3450002006264156.6auto
GFOpen officeOpen-plan office180.0180050977900split × 1116500090027100150.6auto
GFMeeting roomMeeting / conference room30.034510211200split × 2300003004845161.5auto
GFToiletsToilet / washroom24.01856111100none00240152563.5auto
FFOpen officeOpen-plan office240.0240067121011200split × 15225000120037300155.4auto
FFServer roomServer / data / hub room20.01424122100split × 69000010000 (Racks via UPS)212421062.1auto
FloorRoomsm²LightingSmall power (sockets)Split ACCentral HVAC (AHU / FCU)EquipmentTotal WW/m²
GF4274.02,69411,40024,00001,64039,734145.0
FF2260.02,54213,30031,500011,20058,542225.2
Demand per floor and category (board level, after the category demand factors)020406080100floorkWGF · Lighting: 2.4GF · Small power (sockets): 5.7GF · Split AC: 23.3GF · Equipment: 1.532.9GFGF · connected: 39.7FF · Lighting: 2.3FF · Small power (sockets): 6.7FF · Split AC: 30.4FF · Equipment: 10.950.2FFFF · connected: 58.5LightingSmall power (sockets)Split ACEquipmentconnected

Bars: demand of the floor's boards by category (central HVAC = AHU / FCU share at the HVAC panel's factor); dashes: connected load. Plant loads at the panels (lifts, pumps, chillers) are not floor loads — see section 4.

3. Distribution-board schedules

LPDB-GF — GF · TPN 18-way · fed from FP-GF

Connected
39.73 kW
Demand
32.86 kW · 36.51 kVA
Ib
50.8 A
Incomer
80 A FP MCCB isolator
Earth leakage
100 A FP RCCB 30 mA
Unbalance
0.9 %
CktPhDescriptionPointsLoad WIb AMCBWire mm²
1BLighting & 6 A sockets — Reception72821.46 A SP1.5
2BLighting & 6 A sockets — Reception62821.46 A SP1.5
3YLighting & 6 A sockets — Open office104502.26 A SP1.5
4BLighting & 6 A sockets — Open office104502.26 A SP1.5
5RLighting & 6 A sockets — Open office104502.26 A SP1.5
6YLighting & 6 A sockets — Open office104502.26 A SP1.5
7BLighting & 6 A sockets — Open office104502.26 A SP1.5
8RLighting & 6 A sockets — Open office94502.26 A SP1.5
9YLighting & 6 A sockets — Meeting room62721.36 A SP1.5
10RLighting & 6 A sockets — Meeting room62721.36 A SP1.5
11YLighting & 6 A sockets — Toilets72851.46 A SP1.5
12Y16 A sockets (1) — Reception110004.820 A SP4
13RAC unit 1 — Reception115007.220 A SP4
14YAC unit 2 — Reception115007.220 A SP4
15BAC unit 3 — Reception115007.220 A SP4
16R16 A sockets (2) — Open office220009.720 A SP4
17Y16 A sockets (2) — Open office220009.720 A SP4
18B16 A sockets (2) — Open office220009.720 A SP4
19B16 A sockets (1) — Open office110004.820 A SP4
20RAC unit 1 — Open office115007.220 A SP4
21YAC unit 2 — Open office115007.220 A SP4
22BAC unit 3 — Open office115007.220 A SP4
23RAC unit 4 — Open office115007.220 A SP4
24YAC unit 5 — Open office115007.220 A SP4
25BAC unit 6 — Open office115007.220 A SP4
26RAC unit 7 — Open office115007.220 A SP4
27YAC unit 8 — Open office115007.220 A SP4
28BAC unit 9 — Open office115007.220 A SP4
29RAC unit 10 — Open office115007.220 A SP4
30YAC unit 11 — Open office115007.220 A SP4
31REquipment — Open office19004.316 A SP4
32Y16 A sockets (1) — Meeting room110004.820 A SP4
33BAC unit 1 — Meeting room115007.220 A SP4
34RAC unit 2 — Meeting room115007.220 A SP4
35B16 A sockets (1) — Toilets110004.820 A SP4
Phase loads R 13072 · Y 12957 · B 12964 W · demand by category: Lighting 2,694 → 90 % (4.2.2.2 Sl i) = 2,425, Small power (sockets) 11,400 → 50 % (cl. 5.9.2) = 5,700, Split AC 24,000 → 100 % up to 200 m², 85 % beyond: 250 m² → 97.0 % (4.2.2.2 Sl iii) = 23,280, Equipment 1,640 → 100 % largest + 75 % rest (4.2.2.2 Sl ii / xiv) = 1,455 · circuit wiring FRLS Cu, 1.5 mm² lighting / 4 mm² power / 4 mm² AC, earth per IS 3043 / IEC 60364-5-54

LPDB-FF — FF · TPN 18-way · fed from FP-FF

Connected
58.54 kW
Demand
50.25 kW · 55.83 kVA
Ib
77.7 A
Incomer
100 A FP MCCB isolator
Earth leakage
100 A FP RCCB 30 mA
Unbalance
1.1 %
CktPhDescriptionPointsLoad WIb AMCBWire mm²
1YLighting & 6 A sockets — Open office104502.26 A SP1.5
2BLighting & 6 A sockets — Open office104502.26 A SP1.5
3YLighting & 6 A sockets — Open office104502.26 A SP1.5
4BLighting & 6 A sockets — Open office104502.26 A SP1.5
5YLighting & 6 A sockets — Open office104502.26 A SP1.5
6BLighting & 6 A sockets — Open office104502.26 A SP1.5
7RLighting & 6 A sockets — Open office104502.26 A SP1.5
8YLighting & 6 A sockets — Open office94502.26 A SP1.5
9BLighting & 6 A sockets — Server room52421.26 A SP1.5
10R16 A sockets (2) — Open office220009.720 A SP4
11Y16 A sockets (2) — Open office220009.720 A SP4
12B16 A sockets (2) — Open office220009.720 A SP4
13R16 A sockets (2) — Open office220009.720 A SP4
14Y16 A sockets (2) — Open office220009.720 A SP4
15RAC unit 1 — Open office115007.220 A SP4
16YAC unit 2 — Open office115007.220 A SP4
17BAC unit 3 — Open office115007.220 A SP4
18RAC unit 4 — Open office115007.220 A SP4
19YAC unit 5 — Open office115007.220 A SP4
20BAC unit 6 — Open office115007.220 A SP4
21RAC unit 7 — Open office115007.220 A SP4
22YAC unit 8 — Open office115007.220 A SP4
23BAC unit 9 — Open office115007.220 A SP4
24RAC unit 10 — Open office115007.220 A SP4
25YAC unit 11 — Open office115007.220 A SP4
26BAC unit 12 — Open office115007.220 A SP4
27RAC unit 13 — Open office115007.220 A SP4
28YAC unit 14 — Open office115007.220 A SP4
29BAC unit 15 — Open office115007.220 A SP4
30REquipment — Open office112005.816 A SP4
31B16 A sockets (2) — Server room220009.720 A SP4
32RAC unit 1 — Server room115007.220 A SP4
33YAC unit 2 — Server room115007.220 A SP4
34BAC unit 3 — Server room115007.220 A SP4
35RAC unit 4 — Server room115007.220 A SP4
36YAC unit 5 — Server room115007.220 A SP4
37BAC unit 6 — Server room115007.220 A SP4
38RYBRacks via UPS — Server room11000015.520 A TP6
Phase loads R 19483 · Y 19633 · B 19425 W · demand by category: Lighting 2,542 → 90 % (4.2.2.2 Sl i) = 2,288, Small power (sockets) 13,300 → 50 % (cl. 5.9.2) = 6,650, Split AC 31,500 → 100 % up to 200 m², 85 % beyond: 260 m² → 96.5 % (4.2.2.2 Sl iii) = 30,410, Equipment 11,200 → 100 % largest + 75 % rest (4.2.2.2 Sl ii / xiv) = 10,900 · circuit wiring FRLS Cu, 1.5 mm² lighting / 4 mm² power / 4 mm² AC, earth per IS 3043 / IEC 60364-5-54
Phase loading per board (R-Y-B)05 00010 00015 00020 00025 000board (unbalance = (max − min) / max; limit 15 %)WLPDB-GF: 13 072LPDB-FF: 19 483LPDB-GF: 12 957LPDB-FF: 19 633LPDB-GF: 12 964LPDB-FF: 19 425LPDB-GFLPDB-FFR phaseY phaseB phase0.9 %1.1 %

Connected watts per phase of every TPN board after the largest-first R-Y-B allocation; the figure above each group is the unbalance (max − min) / max, limit 15 %.

4. Panels — connected, diversity, demand

MAIN LT PANEL — Ib 177.1 A · incomer 250 A · DF 0.85

FeedsKindConnected WDemand ruleDemand WPhase
Passenger liftlift15,000100 % (4.2.2.2 Sl viii)15,0003
Fire pumpspump45,000100 % largest + 80 % second + 60 % rest (4.2.2.2 Sl vii)45,0003
FP-GFpanel39,734panel demand29,5743
FP-FFpanel58,542panel demand45,2233
Total158,276134,797 × 0.85 = 114,577

FP-GF — Ib 45.7 A · incomer 63 A · DF 0.9

FeedsKindConnected WDemand ruleDemand WPhase
LPDB-GFdb39,734board demand32,8603
Total39,73432,860 × 0.9 = 29,574

FP-FF — Ib 69.9 A · incomer 100 A · DF 0.9

FeedsKindConnected WDemand ruleDemand WPhase
LPDB-FFdb58,542board demand50,2483
Total58,54250,248 × 0.9 = 45,223

Maximum demand 114.6 kW = 127.3 kVA at pf 0.9 → transformer 160 kVA (≈ 80 % loading), DG 160 kVA for full backup — refine with the essential / non-essential split.

5. Final-circuit checks

CheckCircuitsResult
Lighting circuits ≤ 800 W and ≤ 10 points (NBCS 5.4.4.3 mixed circuit of lights, fans and 6 A sockets; a dedicated lighting circuit may take 20 points — the 10-point packing is stricter)20PASS
16 A outlets ≤ 2 per circuit on 4 mm² Cu (NBCS 5.4.4.3)13PASS
General sub-circuits ≤ 3000 W (NBCS 5.4.4.7; design ≈ 2500 W for 20 % growth)33PASS

Final-circuit voltage drop ≤ 3 % from the DB to the last point (NBCS 2026 cl. 6.2; ≤ 6 % transformer → final DB) needs the circuit lengths: it is checked in Electrical layouts (circuits drawn on the plan).

Building planning densities — NBCS 2026 Part D Sec 2 cl. 5.9.2 — planning densities where nothing is specified (informational)

ItemProjectNBCS 5.9.2BasisStatus
Lighting, built-up area9.81≤ 13 W/m²5,236 W / 534.0 m²meets
Power (sockets + AC + equipment), built-up area174.2≥ 55 W/m²93,040 W / 534.0 m², excl. lifts, pumps, fire-fighting, ventilationmeets
Small-power diversity applied50.0≤ 50 %12,350 / 24,700 W demand / connectedmeets

Informational: NBCS 5.9.2 gives these values for planning where nothing else is specified; the room-by-room estimate above governs. Lighting above 13 W/m² or power below 55 W/m² is flagged for review only.

6. Feeder schedule for the power-distribution design

#FromTokWLength mPhasePanel
1MAIN LT PANELPassenger lift15.030.03
2MAIN LT PANELFire pumps45.030.03
3MAIN LT PANELFP-GF29.5740.03●
4MAIN LT PANELFP-FF45.2240.03●
5FP-GFLPDB-GF32.8630.03●
6FP-FFLPDB-FF50.2530.03●

Send to Power Distribution Design for cable sizing, fault levels and the SLD; lengths are project defaults until measured on the plan.

7. Worked examples — from this project

Worked from this project’s own inputs and results — each value can be traced to the schedules above.

Board LPDB-FF — FF (2 rooms, 38 circuits)
the board with the largest demand in this project
Given: System 415 V 3φ / 230 V 1φ, pf 0.9 · Board TPN 18-way, fed from FP-FF
1. Demand — Lighting: Pd per NBCS 4.2.2.2 = 2,542 W → 90 % (4.2.2.2 Sl i) = 2288 W (type of building: office)
2. Demand — Small power (sockets): Pd = Pconn × 50 % = 13,300 W → 50 % (cl. 5.9.2) = 6650 W
3. Demand — Split AC: Pd per NBCS 4.2.2.2 = 31,500 W → 100 % up to 200 m², 85 % beyond: 260 m² → 96.5 % (4.2.2.2 Sl iii) = 30 410 W
4. Demand — Equipment: Pd per NBCS 4.2.2.2 = 11,200 W → 100 % largest + 75 % rest (4.2.2.2 Sl ii / xiv) = 10 900 W
5. Board maximum demand: PMD = Σ Pd = 2,288 + 6,650 + 30,410 + 10,900 = 50 248 W (connected 58,542 W)
6. Apparent power: S = PMD / cosφ = 50,248 / 0.9 / 1000 = 55.83 kVA
7. Design current: Ib = PMD / (√3 · U · cosφ) = 50,248 / (1.732 · 415 · 0.9) = 77.7 A (engine 77.7 A)
8. Incomer: next standard rating ≥ max(1.25 · Ib, 32 A) = 1.25 × 77.7 = 97.1 A = 100 A FP MCCB isolator (ratings 6, 10, 16, 20, 25, 32, 40, 50, 63, 80, 100, 125 … A)
9. Incomer ≥ design current: In ≥ Ib → 100 ≥ 77.7 A PASS (earth leakage: 100 A FP RCCB 30 mA)
10. Phase balance: (max − min) / max ≤ 15 % → R 19483 · Y 19633 · B 19425 W → 1.1 % PASS
Circuit LPDB-FF/1 — Lighting & 6 A sockets — Open office
the most loaded lighting circuit of that board
Given: Load 450 W, 10 points, phase Y · Circuit rule NBCS 2026 Part D Sec 2 cl. 5.4.4.3: mixed circuit (lights, fans, 6 A sockets) ≤ 10 points and 800 W, dedicated lighting ≤ 20 points / 800 W, 6 A socket circuit ≤ 8 nos / 800 W, fans ≤ 10, 16 A outlets ≤ 2 per circuit on 4 mm² Cu; cl. 5.4.4.7 sub-circuit ≤ 3 000 W · CPWD General Specifications Part I: separate circuit per AC
1. Watts per circuit: P ≤ 800 W → 450 W PASS
2. Points per circuit: n ≤ 10 → 10 PASS
3. Design current: Ib = P / (U0 · cosφ) = 450 / (230 · 0.9) = 2.2 A (engine 2.2 A)
4. MCB: next standard rating ≥ max(Ib, 6 A) = 2.2 A = 6 A SP (10 A minimum above 500 W (same rule in Electrical layouts and the CAD circuits))
5. Sub-circuit cap: P ≤ 3 000 W (NBCS 5.4.4.7) → 450 W PASS
6. Wire: regime lighting wire → 1.5 mm² Cu PASS
Building total — MAIN LT PANEL
every board, panel and plant load rolled up to the main LT panel
Given: Feeds 4 — Passenger lift, Fire pumps, FP-GF, FP-FF
1. Sum of incoming demands: Σ Pd,feeds = 15,000 + 45,000 + 29,574 + 45,223 = 134,797 W (sub-panels already × 0.9)
2. Diversity at the main panel: PMD = Σ × DFmain = 134,797 × 0.85 = 114,577 W
3. Maximum demand: S = PMD / cosφ = 114,577 / 0.9 / 1000 = 127.3 kVA
4. Main incomer current: Ib = PMD / (√3 · U · cosφ) = 114,577 / (1.732 · 415 · 0.9) = 177.1 A (incomer 250 A (≥ 1.25 · Ib, min 100 A))
5. Transformer: next size ≥ 1.25 · S = 1.25 × 127.3 = 159.1 kVA = 160 kVA (≈ 80 % loading; DG 160 kVA (next size ≥ S))

8. Standards applied

StandardUsed for
NBCS 2026 (SP 7:2026) Part D Sec 2cl. 4.2.2.2 diversity by type of building (+ note: 50–90 % load factor), 5.4.4.3 / 5.4.4.7 sub-circuit limits, 5.9.2 planning densities, 6.2 voltage drop
IS 732:2019Electrical wiring installations
CPWD General Specifications for Electrical Works Part I (Internal)Sub-circuit limits, wiring sizes, DB construction
ECSBC 2024 cl. 7.3.3, Tables 7.4 / 7.5 / 7.6Lighting power density per room type
IS 3043Earthing
Prepared by
Checked by
Approved by

Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.