SAMPLERainwater — harvesting, roof drainage, recharge pit — this is what your report looks like, generated from demo inputs.Generate yours →2 free designs every day for every signed-in account · 1 design free on sign-in · ₹99 + GST per design (report + Excel + DXF) · free for DesignLink companies
Report ready — use Print → Save as PDF (A4 landscape).
1. Roof harvest (NBCS Table 26): V = 0.8 · Aroof · R / 1000 = 0.8 × 1200 × 800 / 1000 = 768 m³/yr(80 % of gross precipitation)
2. Storage: S = demand · days = 20 × 3 = 60 m³(11 % of the year's demand met (monthly balance))
3. Roof runoff: Q = A · i / 3600 = 1200 × 75 / 3600 = 25 L/s(3.12 L/s and 150 m² per pipe)
4. EN 12056-3 capacity (international): Q = 3.15×10⁻⁴ · f5/3 · d8/3, f = 0.33 = d = 75 = 4.97 L/s(≥ 3.12 L/s → DN 75)
5. NBCS roof area per pipe: RA = 0.084 · d2.5 / I × kmat = 0.084 × 1002.5 / 75 × 1.44 = 161.3 m²(NBCS E2 4.5.11.6.8, Table 25 (PVC × 1.44))
6. Governing down-pipe: RA ≥ Aroof / n and EN capacity ≥ q → DN 100: 161 ≥ 150 m² PASS
7. Storm runoff: V = Σ(A·C) · i · t / 1000 = 1870 × 75 × 1 / 1000 = 140.2 m³
8. Pit capacity: Vpit = 0.35 · πd²/4 · h + (πdh + πd²/4) · k · t + bore = 3.3 + 0.5 + 4.0 = 7.8 m³
9. Pits: n = ⌈V / Vpit⌉ = ⌈140.2 / 7.8⌉ = 18 nos
5. Notes
Runoff coefficients and harvest per NBCS 2026 Part E Sec 2 4.5.11.2 and Table 26 (80 % of gross precipitation on roofs); storage between dry spells, overflow to recharge (4.5.12.3).
Down-pipes: BS EN 12056-3 Wyly–Eaton (f = 0.33) is the international method; for India NBCS 2026 Table 25 / RA = 0.084·d^2.5/I governs (cast iron as printed, PVC × 1.44).
Infiltration rates are typical — a percolation test governs; bore yields need the CGWB / hydrogeologist input.
NBCS E2 4.5.12.3.1 / 4.5.12.4: divert the first flush, chlorinate stored water to ≈ 1 mg/L residual, silt trap at every recharge structure, no sewage or oily run-off, recharge wells end ≥ 5 m above the highest water table; pit number and type per local / state bye-laws (4.5.12.1).
6. Standards and references
CPHEEO Manual on Sewerage and Sewage Treatment Systems (2013), Part A — Engineering — design of sewers (flows, peak factors, Manning, velocities, d/D, cover, manholes): Sewer network design rules (India)
BS EN 12056-3 — Gravity drainage systems — roof drainage: Gutter and downpipe capacities
CGWB Manual on Artificial Recharge of Ground Water (2007) — Central Ground Water Board manual: Recharge pit / trench sizing
NBCS 2026 (SP 7:2026) Part E Sec 2 — National Building Construction Standards — Drainage and sanitation: Sanitary fixtures by occupancy (Tables 1–17), DFU, stacks, vents, building drains, rainwater pipes (Table 25)
Prepared by
Checked by
Approved by
Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.