| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| G1 | Design basis report issued and approved; codes and editions listed (NBCS 2026 / SP 7:2026 stated as the building code) | NBCS 2026 Part A (p. 46–55) / contract | Open | |
| G2 | Drawings, calculations and schedules cross-referenced (same revision, same tags) | PMC procedure | Open | |
| G3 | Statutory approvals identified: fire NOC (or self-certification where the Table 7A–7J row allows it), electrical inspectorate, pollution, water board | NBCS 2026 Part F Tables 7A–7J (p. 2791–2819) / CEA Regulations 2023 | Open | |
| G4 | Shaft, plant-room and ceiling-void space adequate for the services shown; service shafts fire-rated and fire-stopped (120 min) | NBCS 2026 Part D Sec 2 cl. 4.3, 4.6 (p. 1680–1681) / Part F cl. 3.5.4.4 (p. 2756) | Open | |
| G5 | Occupancy group and sub-division, building height and largest floor area stated; high-rise provisions applied when the building is 24 m or above in height (NBC 2016: 15 m) | NBCS 2026 Part F cl. 2.39 (p. 2745), cl. 3.1 (p. 2748) / Part A (p. 48) | Open |
| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| E1 | Load estimate with demand and diversity factors; transformer and DG sized on the diversified load | CPWD GS Part I cl. 2 / NBCS 2026 Part D Sec 2 cl. 6.1.1 (p. 1707) | Open | |
| E2 | SLD consistent with the cable schedule: breaker ratings, cable sizes, runs, bus ratings | IS 732 / IS 8623 | Open | |
| E3 | Voltage drop within limits from source to farthest load (CPWD 3 % lighting, 5 % power; NBCS: below 6 %) | IS 732 / CPWD GS cl. 1.3 / NBCS 2026 Part D Sec 2 cl. 5.6 Note a) (p. 1700) | Open | |
| E4 | Short-circuit withstand of cables, breakers and busbars at the design fault level | IEC 60909 / IS 13947 | Open | |
| E5 | Earthing: pit numbers, strip sizes, resistance target, equipotential bonding, LPS class and mesh | IS 3043 / IS/IEC 62305 / NBCS 2026 Part D Sec 2 cl. 11 (p. 1761) | Open | |
| E6 | Lighting: illuminance and uniformity per space type, escape lighting and exit signage on escape routes, LPD within ECBC | NBCS 2026 Part D Sec 1 Table 6 (p. 1547) / Part F cl. 3.5.6 (p. 2761) / IS 3646 / ECBC 2017 | Open | |
| E7 | Circuit loading within CPWD limits (800 W / 10 points), wiring and conduit sizes, RCCB protection | CPWD GS Part I cl. 3 | Open | |
| E8 | DG: essential loads, step loading, exhaust, fuel storage, acoustic enclosure, CPCB norms | CPWD GS Part VII / CPCB / NBCS 2026 Part D Sec 2 cl. 4.3 (p. 1680) | Open | |
| E9 | UPS: critical loads, backup time, battery room ventilation | IS 16242 / IEEE 485 | Open | |
| E10 | Cable trays and risers: fill, supports, fire stopping at floor crossings (120 min), armoured / metal-conduit cables in shafts | IEC 61537 / NBCS 2026 Part F cl. 3.5.4.4 (p. 2756) | Open | |
| E11 | Emergency power for the life-safety systems: fire pumps, pressurisation and smoke venting, fireman's / all lifts, exit signage, escape lighting, fire alarm, PA, door hold-open devices | NBCS 2026 Part F cl. 3.5.5.2 (p. 2757) | Open |
| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| E1 | ICT: entrance facility and telecom rooms located and sized; an additional TR where the horizontal cable from the floor distributor exceeds 90 m; horizontal cabling media stated | NBCS 2026 Part D Sec 6 cl. 3.1, 3.1.3.2 (p. 2468–2471), 3.4.1.1 (p. 2483) | Open | |
| E2 | Wi-Fi: access points to IEEE 802.11 ax/be or later, coverage and capacity planned, APs cabled to the floor distributor | NBCS 2026 Part D Sec 6 cl. 3.2.5 (p. 2476) | Open | |
| E3 | BMS: monitored / controlled systems listed (substation, HVAC, lighting, energy, lifts and escalators, fire safety, security, car park); I/O summary with spare; lift–BMS interface | NBCS 2026 Part D Sec 2 cl. 10.4 (p. 1747) / Sec 3 cl. 15 (p. 2044) / Sec 5 cl. 9.8 (p. 2321) | Open | |
| E4 | BMS – fire alarm integration: FA programmed to operate AHUs, pressurisation, smoke management and fire-door release; FA panel monitors tank water levels, hydrant / sprinkler zone pressures, pump ON/OFF and supervised isolation valves | NBCS 2026 Part F cl. 4.9 b), j) (p. 2789–2790) / Part D Sec 2 cl. 10.4 (p. 1747) | Open |
| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| F1 | Fire-fighting installations per the occupancy row of Tables 7A–7J for the occupancy, height and floor area (extinguishers, hose reel, down-comer, wet riser, yard hydrant, sprinklers, detection, PA); level of protection CL-1…8 / HL-1…6 stated | NBCS 2026 Part F Tables 7A–7J (p. 2791–2819) | Open | |
| F2 | Sprinkler hazard classification, design density and area of operation; head spacing and coverage; system pressure ≤ 12 bar; ≤ 4 500 m² per floor per installation control valve | IS 15105 / NBCS 2026 Part F cl. 5.1.3 (p. 2828) / NFPA 13 | Open | |
| F3 | Hydraulic calculation for the remote area; fire-water demand and pump from Table 7K / 7M for the level of protection; storage = demand × duration (30–120 min, Table 7K / 7M Note 2) | IS 15105 / NBCS 2026 Part F Tables 7K, 7M (p. 2820–2821) | Open | |
| F4 | Fire pump house: electric pump with a standby of equivalent capacity and a jockey pump; directly accessible, not below the second basement, 120 min fire walls and doors; soft starter / VFD; pump supply on the emergency source; shut-off ≤ 12 bar above 60 m | IS 12469 / NBCS 2026 Part F cl. 5.1.2.2 (p. 2827–2828), Tables 7K / 7M Note 1, cl. 3.5.5.2 a) (p. 2757) | Open | |
| F5 | Hydrant system: ≥ 3.5 bar at the hydraulically remote and highest hydrant and ≤ 7.0 bar at any hydrant (orifice plates / pressure-reducing devices below); riser / main size per Table 8; landing valves on every floor; yard hydrants ≤ 45 m apart | NBCS 2026 Part F cl. 5.1.1 f) (p. 2822), Table 8 (p. 2827) / IS 13039 / IS 3844 | Open | |
| F6 | Fire detection and alarm per Tables 7A–7J column (9); detectors also in electrical shafts and lift machine rooms where cl. 4.9 e) applies; FA panels networked peer-to-peer / redundant; interfaces with HVAC, lifts, doors | IS 2189 / NBCS 2026 Part F cl. 4.9 a), e), f) (p. 2789–2790) | Open | |
| F7 | Public address and voice evacuation provided where Tables 7A–7J column (10) require it for the occupancy row; pre-recorded messages in English, Hindi and the vernacular, alerting the fire zone and the surrounding zones / floors; PA on the emergency supply and at the fire command centre | NBCS 2026 Part F Tables 7A–7J col. (10) (p. 2791–2819), cl. 4.9 c) (p. 2789), cl. 3.5.5.2 g) (p. 2757), cl. 3.5.11 a) (p. 2765) | Open | |
| F8 | Means of egress: occupant load, exit and stair widths, number of exits, travel distance and dead ends for the occupancy and construction type | NBCS 2026 Part F cl. 4.4.2 (p. 2771–2772), Tables 2–4 (p. 2769–2775) | Open |
| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| P1 | Water demand and storage: population × LPCD, UGT / OHT capacities, fire reserve (Part F demand × duration) | NBCS 2026 Part E Sec 1 cl. 4.1, Table 1 (p. 2520–2523), cl. 4.4 (p. 2526) / CPHEEO | Open | |
| P2 | Domestic water risers sized on fixture units; residual pressure at the top floor; booster where needed | NBCS 2026 Part E Sec 1 Tables 2, 3 (p. 2530–2531) / IS 2065 | Open | |
| P3 | Drainage stacks, vents and building drains sized on fixture units; two-pipe / one-pipe system stated | NBCS 2026 Part E Sec 2 Tables 18–23 (p. 2616–2626) / IS 1742 / IS 5329 | Open | |
| P4 | Storm-water drainage: rainfall intensity, roof outlets, pipes and drains, rainwater harvesting | NBCS 2026 Part E Sec 2 Table 25 (p. 2643), Table 26 (p. 2647) / IS 1742 / CGWB | Open | |
| P5 | STP / sewer connection: capacity, treated-water reuse, discharge standards | CPHEEO / CPCB | Open |
| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| H1 | Heat load by zone with design conditions, occupancy, lighting and equipment gains, fresh air | ISHRAE / ASHRAE 62.1 | Open | |
| H2 | Duct and pipe sizing: velocities, friction, fan static and pump head; insulation thickness | ISHRAE / SMACNA / ECBC Tables 5-8, 5-9 | Open | |
| H3 | Plant efficiency per ECBC (chiller COP, fan power, VFDs, economizer) | ECBC 2017 ch. 5 | Open | |
| H4 | Ventilation of basements, kitchens, toilets, plant rooms; smoke exhaust and pressurisation where required | NBCS 2026 Part D Sec 3 cl. 12.6.2 (p. 1997), 14.3 (p. 2034) / Part F cl. 4.6 (p. 2786–2787) | Open |
| # | Requirement / check | Reference | Status | Remark |
|---|---|---|---|---|
| E1 | ECBC compliance route stated (prescriptive / whole building); envelope, lighting, HVAC and electrical requirements met | ECBC 2017 | Open | |
| E2 | Renewable energy provision (RE generating zone / rooftop PV) and solar water heating | ECBC 2017 cl. 7.4 / local bye-laws | Open | |
| E3 | Energy metering per end use; BMS points for major plant | ECBC 2017 cl. 7.2.4 / NBCS 2026 Part D Sec 3 cl. 15.1 (p. 2044) | Open |
Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.