calc.designlink.in
Source sizing — transformers, DG, UPS
Sample project — Tower A · Indian regime · NBCS 2026 · growth 20 %
Generated 28 Nov 2026 16:09 From the classified load list Project code SAMPLE
Transformers
3 × 400 kVA
DG sets
1 × 400 kVA
UPS
2 × 100 kVA
Utility demand
514.5 kVA
DG demand
265.1 kVA
Checks
all pass
1. Load classification
Load
Panel
Kind
Class
F&LS
Connected kW
Demand kW
Starting
Starting kVA
Note
LDB-GF
db
Essential (DG-backed)
25.0
25.0
no motor / static
PDB-GF
db
Non-essential (utility only)
40.0
40.0
no motor / static
HVAC PANEL
hvac
Non-essential (utility only)
180.0
180.0
VFD (1.2 ×)
282.4
LIFT-1
lift
Essential (DG-backed)
●
15.0
15.0
VFD (1.2 ×)
23.5
FIRE PUMP
pump
Fire-fighting (DG / dedicated)
●
75.0
75.0
star-delta (2.5 ×)
245.1
SERVER ROOM
ups
Critical (UPS)
60.0
60.0
no motor / static
WATER PUMPS
pump
Essential (DG-backed)
22.0
22.0
DOL (6 × FLC)
172.5
F&LS = fire and life-safety load per NBCS 2026 Part D Sec 2 cl. 4.2.1(jj) / Part F 3.5.5.2: fire pumps, pressurisation and smoke venting, fireman's lifts including all lifts, exit and emergency lighting, fire alarm, PA, door hold-open devices, fire-control-room lighting — normal + standby generator with changeover.
Class
Demand kW
Diversity
Diversified kW
Essential (DG-backed)
62.0
0.9
55.8
Non-essential (utility only)
220.0
0.85
187.0
Critical (UPS)
60.0
1.0
60.0
Fire-fighting (DG / dedicated)
75.0
1.0
75.0
2. Transformers
Item
Value
Utility demand (all classes, UPS as input kVA, +growth)
514.5 kVA
Units in service / installed
2 / 3 (N+1)
Required per unit at ≤ loading
321.6 kVA
Selected
3 × 400 kVA
Loading with all units
64.3 %
Loading with one unit out
64.3 %
LV full-load current per unit
556 A
Prospective LV fault (Z 5.0 %)
11.1 kA per unit
3. DG sets
Item
Value
DG demand (essential + fire + UPS input, +growth)
265.1 kVA
Site derating
× 0.991 (altitude 300 m → −0.0 %, ambient 45 °C → −0.9 %)
Largest single step
245.1 kVA → rating ≥ 176.5 kVA for the 20 % dip, ≥ 350.1 kVA for the 70 % step
Governed by
F&LS simultaneous start (step)
All F&LS starting together (NBCS 4.2.1 jj)
268.6 kVA in one step → rating ≥ 193.4 kVA (dip), ≥ 383.7 kVA (step); dip at the selected set 10.9 %
Selected
1 × 400 kVA (396.4 kVA each at site)
Loading
66.9 %
Fuel at 75 % load (approx.)
63.0 L/h
Loading sequence
Step
Load
Kind
Step kVA
Running kVA
Before kVA
Transient dip %
Result
1
FIRE PUMP
Fire-fighting · star-delta (2.5 ×)
245.1
83.3
0.0
10.0
PASS
2
WATER PUMPS
Essential · DOL (6 × FLC)
172.5
24.4
83.3
7.3
PASS
3
LIFT-1
Essential · VFD (1.2 ×)
23.5
16.7
107.8
1.1
PASS
4
LDB-GF
block load (static)
25.0
25.0
124.4
1.1
PASS
5
UPS input (rectifier walk-in)
UPS
90.8
90.8
149.4
4.0
PASS
Transient dip per step ΔV ≈ X''d·S / (G + X''d·S) with X''d = 18 % — confirm with the alternator's transient curve; fire pump starts first on an unloaded set.
10.3.2 (e): 4-pole for 3-phase UPS, double-pole for single-phase
Isolation transformer (10.3.2 a)
not provided (optional)
Runtime at 100 % design load — new / end of life
48 / 36 min
required 30 min
Output protection (10.3.4 c)
shut-down on overload / short circuit; warning label where auto-restoration is enabled
5. Checks
Check
Result
Transformer loading ≤ 80 % with 2 unit(s) in service
PASS
N+1: full load carried with one transformer out (≤ 100 %)
PASS
DG loading ≤ 80 % of site rating
PASS
DG loading ≥ 30 % (no wet stacking)
PASS
Every loading step: transient dip ≤ 20 % and step ≤ 70 % of site rating
PASS
Fire pumps on the DG (NBCS 4.2.1 jj: normal + standby generator with changeover)
PASS
Generator takes the starting current of all F&LS loads together (NBCS 4.2.1 jj / Part F 3.5.5.2): 268.6 kVA in one step → dip 10.9 % ≤ 20 %, step ≤ 70 % of rating
PASS
All lifts on the standby (DG) supply — fireman's lifts including all lifts are F&LS loads (NBCS 4.2.1 jj 3)
PASS
UPS 2 × 100 kVA for 80.0 kVA / 72.0 kW at ≤ 80 % loading
Dedicated UPS neutral earth pits (IT), interconnected below soil with the other earth pits
PASS
UPS room ventilated / air-conditioned against thermal runaway
PASS
Battery space well ventilated (H₂ / O₂ evolution)
PASS
Acid-resistant tiles / coating on the battery-room floor
PASS
UPS-fed circuits marked so that mains isolation is not taken as dead
PASS
Circuit breakers: input 4P 160 A ≥ 1.25 × 126 A, output 4P 200 A ≥ 1.25 × 139 A
PASS
Day-oil tank with the set < 1 000 L (≤ 1 500 L in a separate room next to the DG room), bulk fuel underground under the Petroleum Act — NBCS 4.3.3(a); 1 000 L ≈ 15.9 h at 75 % load of all sets.
DG location: ground floor or first basement only (first floor only with a dedicated approach in a separate fire compartment), forced ventilation in a basement — NBCS 4.3.1; DG room separated by 120 min fire-resisting walls and doors — Part F 3.5.5.4.
F&LS panel in a fire-safe zone, fed by fire-survival cables / fire-proof enclosures or an alternate route through the adjoining compartment; FA and PA cables in metal conduit or armoured — NBCS 4.2.1(jj).
6. Room areas — NBCS 2026 Part D Sec 2 Annex C / D (guidance)
Space
Area
Basis
Transformer room, min (Annex C)
49.5 m²
row 3 × 400 kVA
Substation incl. HV / MV panels, without generators (Annex C)
167 m²
suggested face width 18 m; clear height = equipment + 1 200 mm below the beam soffit (Note 2 / 4.2.1 ff)
Generator room, each set (Annex D) × 1
100 m² each → 100 m²
row 480 kVA; clear height 4.2 m below the beam soffit; covers the day tank, not bulk fuel (Note 3)
7. Worked examples — from this project
Worked from this project’s own inputs and results — each value can be traced to the schedules above.
2. Site derating: f = 1 − 3.5 %/300 m above 1000 m − 1 %/5.5 °C above 40 °C = altitude 300 m → −0.0 %, ambient 45 °C → −0.9 % = 0.991 (ISO 3046 / ISO 8528 practice)
3. Running requirement per set: S / loading / n / f = 265.1 / 0.8 / 1 / 0.991 = 334.4 kVA
4. Largest start — FIRE PUMP: Sst = Pm / η / cosφ × kstart = 75 / 0.9 / 0.85 × 2.5 = 245.1 kVA(star-delta (2.5 ×))
5. Rating for the voltage dip: G ≥ X″d · Sst · (1 − d) / d = 0.18 · 245.1 · 0.8 / 0.2 = 176.5 kVA
6. Rating for the step capability: G ≥ Sst / step = 245.1 / 0.7 = 350.1 kVA
7. Required per set: max(running, dip, step) / n / f = max(334.4, 178.1, 353.4) = 387.2 kVA(next standard size from 200, 250, 320, 380, 400, 500, 600, 625 … kVA)
9. All F&LS loads starting together: SF&LS = Σ Sst (motors) + Σ S (static F&LS) = 23.5 + 245.1 = 268.6 kVA(NBCS 4.2.1(jj) / Part F 3.5.5.2: LIFT-1, FIRE PUMP)
10. Rating for that one step: G ≥ max(X″d · S · (1 − d) / d, S / step) = max(0.18 · 268.6 · 0.8 / 0.2, 268.6 / 0.7) = 383.7 kVA(added to the max() above)
11. F&LS simultaneous start: ΔV ≤ 20 % and S ≤ 70 % of Gsite → 10.9 %, 268.6 / 396.4 kVA PASS
12. Selected: 1 in service = 1 × 400 kVA(396.4 kVA each at site)
CPWD General Specifications for Electrical Works Part VII (DG sets)
DG selection, installation
NBCS 2026 (SP 7:2026) Part D Sec 2
4.2.1(jj) F&LS supply — generator takes the starting current of all F&LS loads; 4.3 DG location, room, day tank; 5.2.5 / 10.7.3 EV not on DG; Annex C / D room areas
NBCS 2026 Part F
3.5.5.2 emergency power for F&LS (all lifts), 3.5.5.4 standby supply
IEEE 485 / IS 16242
Battery sizing / UPS
CEA (Technical Standards for Connectivity)
Standby generation
Prepared by
Checked by
Approved by