Technical specification

Sample project — Tower A · Sample project — Tower A · Private (detailed)
Generated 28 Nov 2026 16:09
Assembled from the clause library, project values and approved makes
Project code SAMPLE
Profile
Private (detailed)
Sections
1
Clauses
13
Standards
15
Words
4644
Unresolved tokens
0
ItemValue
ProjectSample project — Tower A
LocationGurugram
ClientSample client
Consultant—
DocumentTS-E-001 · R0 ·

Contents

SECTION I - LT CABLES, LAYING AND TERMINATION

1. Scope of work
2. Codes and standards
3. General
4. Cable types, voltage grade and conductor material
5. Flame retardant low smoke halogen free requirement for occupied areas and escape routes
6. Fire survival cables for fire pumps, firefighters lift, pressurisation fans, smoke extract fans, fire alarm and emergency lighting
7. Cable sizing, derating and voltage drop
8. Laying underground, on trays and in shafts
9. Segregation of MV, LV, control and extra low voltage circuits
10. Terminations, lugs and glands
11. Identification and core ferruling
12. Testing
13. Measurement

SECTION I - LT CABLES, LAYING AND TERMINATION

1. Scope of work

Work under this section shall consist of furnishing all labour, materials, equipment and appliances necessary and required to completely install the 1.1 kV grade low tension power, control and fire survival cables of the installation, their laying, termination, identification and testing as required by the drawings and specified hereinafter or given in the Schedule of Quantities.

Without restricting to the generality of the foregoing, the work shall include but not be limited to the following: -

  1. a) Supply of 1.1 kV grade power cables with cross linked polyethylene or polyvinyl chloride insulation, armoured or unarmoured, of the conductor material, size and number of cores given in the Schedule of Quantities.
  2. b) Supply of cables with a flame retardant low smoke halogen free sheath and insulation for all runs within occupied areas, escape routes, staircases, lift lobbies and shafts.
  3. c) Supply of fire survival cables of the circuit integrity classification specified for the fire pumps, the firefighters lift, the pressurisation fans, the smoke extract fans, the fire alarm system and the emergency lighting.
  4. d) Supply of control cables, screened cables and extra low voltage cables of the sizes and types given in the Schedule of Quantities.
  5. e) Laying of cables underground in trenches, in ducts and sleeves, on cable trays and ladders, in shafts and risers, in conduits and on saddles, including all supports, clamps, cleats and dressing.
  6. f) Segregation of the medium voltage, low voltage, control and extra low voltage circuits with the separation distances specified.
  7. g) Termination of all cables with double compression glands, crimped lugs, armour clamps and earth tags, and the making off of screens and drain wires.
  8. h) Identification tags at both ends and at all intermediate accessible positions, phase identification and core ferruling of all control cores.
  9. i) Testing of every cable for insulation resistance, continuity, phase sequence and earth continuity, and the sheath integrity test of buried cables.
  10. j) Cable schedules, as built drawings, drum test certificates and the fire survival test certificates of the cables supplied.

2. Codes and standards

The work shall comply with the latest editions of the following codes and standards and with the statutory regulations in force at the time of execution:

  1. a) IS 7098 — Cross-linked polyethylene insulated PVC sheathed cables up to 1100 V
  2. b) IS 1554 — PVC insulated (heavy duty) electric cables up to 1100 V
  3. c) IS 694 — PVC insulated cables for working voltages up to 1100 V
  4. d) IS 17048 — Fire-survival cables for fixed installations
  5. e) IS 8130 — Conductors for insulated electric cables and flexible cords
  6. f) IS 10810
  7. g) IS 10418
  8. h) IS 1255
  9. i) IS 732 — Code of practice for electrical wiring installations
  10. j) IEC 60332-3
  11. k) IEC 61034
  12. l) IEC 60754-2
  13. m) IEC 60331
  14. n) BS 6387 — Fire-resistant cables — performance requirements (CWZ) / enhanced 120 min
  15. o) EN 50200

3. General

All low tension cables shall be of 1.1 kV grade, suitable for a 415 V plus or minus ten per cent, three phase four wire, 50 Hz plus or minus three per cent solidly earthed system, and shall be rated for continuous operation at a design ambient temperature of 50 deg C in a hot, dry and dust laden atmosphere. Cross linked polyethylene insulated cables shall conform to IS 7098 (Part 1), polyvinyl chloride insulated cables to IS 1554, single core wires and flexible cables to IS 694, halogen free cables to IS 17048, conductors to IS 8130, test methods to IS 10810 and drums to IS 10418, and the installation shall comply with IS 1255 and IS 732:2019.

Cables shall be supplied in non returnable drums with both ends sealed, shall be marked along the sheath at intervals of not more than one metre with the manufacturer name, voltage grade, size and year of manufacture, and shall be of the current year of manufacture. Each drum shall be accompanied by a works test certificate, and for fire survival and halogen free cables the type test certificates for the fire performance properties shall also be furnished. Drums shall be stored on a firm level surface, shall be rolled only in the direction marked, and shall not be stored flat.

The Contractor shall prepare a complete cable schedule for approval before ordering, giving for every circuit the designation, origin, destination, type, voltage grade, size, number of cores, method of installation, route length with the vertical rise, the derated current rating, the voltage drop and the earth fault loop impedance. Cables shall be ordered only after the schedule is approved, and drum lengths shall be selected so that no joint is required in any low tension power cable; straight through joints in low tension cables shall not be permitted except with the written approval of the Project Manager.

All cables shall terminate in a gland plate and shall be provided with an accessible slack of not less than one metre at each end for future re termination. Cables shall not be laid in a position where they are exposed to a hot surface, to oil, to a chemical or to mechanical damage, and shall maintain a clearance of not less than 500 mm from an insulated exhaust pipe or any other hot service. Where a cable is unavoidably exposed to sunlight in an external run, an ultraviolet resistant sheath shall be provided.

4. Cable types, voltage grade and conductor material

Power cables shall be of 1.1 kV grade with stranded aluminium or copper conductors as given in the Schedule of Quantities, cross linked polyethylene insulated with a maximum continuous conductor temperature of 90 deg C and a short circuit temperature of 250 deg C, laid up with fillers, with an extruded inner sheath, galvanised steel strip or wire armour for multicore cables and aluminium or non magnetic armour for single core cables, and an extruded outer sheath. Cables of cross section 6 sq mm and below in the power and control categories, and all final sub circuit wiring, shall be of copper conductor.

Conductors of 16 sq mm and above may be of aluminium where the Schedule of Quantities so states, but the cables feeding the fire pumps, the firefighters lift, the pressurisation and smoke extract fans, the fire alarm system, the emergency lighting, the uninterruptible power supply distribution and all control circuits shall be of copper conductor throughout regardless of size. Where an aluminium conductor is terminated on a copper or tinned copper terminal, a bimetallic lug or a bimetallic washer arrangement shall be used and the joint shall be protected against the ingress of moisture.

Control cables shall be of copper conductor of not less than 2.5 sq mm for current transformer circuits and 1.5 sq mm for other control, alarm and indication circuits, with not less than twenty per cent spare cores subject to a minimum of two spare cores in every cable, and shall be armoured where laid outside a panel or a conduit. Cables for analogue signals, communication and extra low voltage systems shall be individually or collectively screened with an aluminium mylar tape and a tinned copper drain wire as required by the system, and the screen shall be earthed at one end only unless the equipment manufacturer requires otherwise.

5. Flame retardant low smoke halogen free requirement for occupied areas and escape routes

All cables installed within the buildings, in occupied areas, in corridors, in lift lobbies, in staircases and escape routes, in electrical and service shafts and in false ceiling voids shall have insulation and sheath of a flame retardant low smoke halogen free compound conforming to IS 17048, and shall satisfy the following performance requirements, each supported by a type test certificate from an accredited laboratory for the compound and the construction offered: -

PropertyRequirementTest standard
Flame propagation on a vertically mounted bunched cableCategory A or A F/R as stated in the Schedule of QuantitiesIEC 60332-3
Smoke density, light transmittance in a three cubic metre chamberNot less than sixty per cent light transmittanceIEC 61034
Halogen acid gas emission and conductivity of the aqueous solutionHalogen content not more than 0.5 per cent; pH not less than 4.3 and conductivity not more than 10 microsiemens per millimetreIEC 60754-2
Oxygen index and temperature index of the compoundOxygen index not less than thirty per cent; temperature index not less than 250 deg CRelevant part of IS 17048

The halogen free requirement shall apply to the insulation, the inner sheath, the fillers, the binder tapes and the outer sheath alike, and a cable in which only the outer sheath is of a halogen free compound shall not be accepted. Where the cable is armoured, the armour bedding shall also be of the halogen free compound. The colour of the outer sheath shall be as approved so that the halogen free cables can be distinguished on site from ordinary polyvinyl chloride sheathed cables.

Cables with a polyvinyl chloride outer sheath may be used only for buried runs outside the building footprint and for runs in an open service yard, and shall be changed to a halogen free type at the point of entry into the building where the drawings so require. All cable accessories used in the occupied areas, including the glands, the shrouds, the ties, the identification tags and the fire stopping, shall be of materials which are consistent with the low smoke and halogen free requirement.

6. Fire survival cables for fire pumps, firefighters lift, pressurisation fans, smoke extract fans, fire alarm and emergency lighting

The circuits which are required to remain in operation during a fire shall be wired in fire survival cable, and these shall comprise as a minimum the supply to the fire pumps and the jockey pump, the supply to the firefighters lift and its controls, the supply to the staircase and lift lobby pressurisation fans, the supply to the smoke extract fans and their dampers, the fire alarm and voice evacuation circuits, the supply to the emergency and escape lighting, and the supply to the fire control panel. In this project the pressurisation and smoke extract circuits arise in the Building 1 and the Building 2, which are the only buildings exceeding 15 m in height, and the remaining categories arise in all the buildings as shown on the drawings.

Fire survival cables shall be of copper conductor with a mineral or mica glass tape barrier under a cross linked insulation and a flame retardant low smoke halogen free sheath, armoured where laid outside a conduit, and shall satisfy the circuit integrity requirements of the following tests, with the certificates furnished for the exact construction and size range offered: -

  1. a) Resistance to fire alone under the conditions of IEC 60331, maintaining circuit integrity at 750 deg C for a period of not less than ninety minutes.
  2. b) Fire with water and fire with mechanical shock under the classification CWZ of BS 6387:2013, that is resistance to fire alone at 950 deg C for three hours, resistance to fire with water and resistance to fire with mechanical shock.
  3. c) Circuit integrity under fire with mechanical shock in accordance with EN 50200:2015 with the classification PH 120 for the cables of the fire alarm and voice evacuation system.
  4. d) Flame propagation to IEC 60332-3, smoke density to IEC 61034 and halogen acid gas emission to IEC 60754-2 in the same manner as the halogen free cables.

Fire survival cables shall be run on a route which is as far as practicable within a fire rated shaft or within a protected area, shall be segregated from all other cables by a clear distance of not less than 300 mm or by a fire rated barrier, and shall be supported on mild steel or hot dip galvanised steel trays and clamps only; plastic ties, plastic trunking and plastic saddles shall not be used at any point on a fire survival circuit. The support spacing shall be not more than that stated in the fire test certificate for the tested configuration, and the fixings shall be of steel anchors which retain their strength at the test temperature.

Terminations, glands, lugs and fire stopping used on a fire survival circuit shall be of a type recommended by the cable manufacturer for use with that cable so that the circuit integrity of the whole installation is preserved, and the termination sequence shall be carried out strictly to the manufacturer instruction. No joint shall be made in a fire survival cable. Every fire survival circuit shall be labelled at both ends and at every accessible position with a distinctive red tag marked with the circuit designation and the words indicating that it is a fire survival circuit.

7. Cable sizing, derating and voltage drop

Cable sizes stated in the Schedule of Quantities are based on the continuous current of the circuit, the rating and characteristic of the protective device, the short circuit withstand of the conductor for the actual clearing time, the earth fault loop impedance required for the operation of the protection within the permitted disconnection time, and the voltage drop limits of three per cent for lighting circuits and five per cent overall from the origin of the installation to the point of utilisation. The Contractor shall verify every size against the actual route length and installation condition and shall report any deficiency before ordering.

The base current rating of the cable shall be derated for the ambient air temperature of 50 deg C for cables in air, for the ground temperature of 40 deg C and a soil thermal resistivity of 150 deg C cm per watt for buried cables, for the depth of laying, for the grouping of circuits on a tray or in a trench, and for the method of installation, and the derated rating shall in every case be not less than the rating of the protective device. Cables laid on a tray shall be in a single layer with a clear spacing of not less than one cable diameter for power cables, and multi layer stacking of power cables shall not be permitted.

Where the connected load includes a significant proportion of non linear equipment, the neutral conductor shall be sized for the triplen harmonic current and shall be of the same cross section as the phase conductor, or of twice the phase cross section where the harmonic content so requires and the Schedule of Quantities so states, and the derating of the cable for harmonic loading shall be applied. The voltage drop calculation shall be carried out using the alternating current resistance at the working temperature and the reactance of the cable, and shall include the drop in the bus duct and in the sub main so that the overall limit of five per cent is demonstrated for the most remote point of utilisation.

The earth fault loop impedance of every final circuit shall be calculated and shall be verified by measurement after installation, and shall be low enough for the protective device to disconnect the fault within the time required by IS 732:2019 for the type of circuit and the system earthing. Where the calculation shows that the loop impedance cannot be met, the protective conductor cross section shall be increased or a residual current protective device shall be provided as directed by the Project Manager. The complete sizing calculation for every circuit shall be submitted in a tabulated form for approval.

8. Laying underground, on trays and in shafts

Low tension cables laid direct in the ground shall be laid at a depth giving a cover of not less than 0.9 m, or 0.75 m under areas which carry no vehicular traffic, on a compacted sand bedding of not less than 75 mm with a further 75 mm of sand over the cable, protected by bricks or precast covers, with a warning tape at not more than 300 mm below the finished level and route markers at intervals not exceeding 30 m, in the manner described in Section II. The horizontal clear spacing between adjacent low tension cables shall be not less than 150 mm, and the spacing from a high tension cable shall be not less than 300 mm with the high tension cable at the lower level.

Cables on trays shall be laid in a single layer, dressed straight and parallel without crossing, and shall be secured to the tray at intervals not exceeding one metre on horizontal runs and 750 mm on vertical runs by aluminium or hot dip galvanised steel clamps or by ties of a halogen free material, with a cushioning strip where the cable bears on a sharp edge. Power cables and control cables shall be laid on separate trays, or on the same tray with the separation specified, and the tray shall not be loaded beyond the limits given in Section VII. Each cable shall be identified at every tray junction and at every change of direction.

In vertical shafts and risers, cables shall be supported at every floor and at intermediate positions not exceeding 1.5 m by clamps which grip the cable over its full circumference without crushing it, so that the whole weight of the vertical run is not carried by the termination. At every floor crossing the opening around the cables shall be sealed by an approved fire stopping system of a rating not less than that of the floor, applied after the cables are finally dressed, and the seal shall be labelled. A kerb of not less than 50 mm shall be provided around every floor opening in a shaft.

Cables in conduits shall be drawn in only after the conduit system is complete, cleaned and swabbed, with the number of cables limited so that the space factor does not exceed forty per cent, and no joint shall be made inside a conduit. The minimum internal bending radius shall be twelve times the overall diameter for a multicore cross linked polyethylene cable and fifteen times for a single core cable, and the radius at a fire survival cable shall be as specified by its manufacturer. Cables shall not be laid in a lift shaft, in a plumbing shaft or in a duct which carries a gas or fuel pipe.

9. Segregation of MV, LV, control and extra low voltage circuits

Circuits of different categories shall be segregated so that a fault or an induced disturbance in one category cannot affect another, and the following minimum clear separations shall be maintained where cables of different categories run parallel on trays or in a common trench, the separation being measured between the nearest surfaces: -

CategoriesMinimum clear separation
Medium voltage power cables of 415 V class and low voltage control cables300 mm, or a sheet steel barrier bonded to earth
Medium voltage power cables and extra low voltage, fire alarm or communication cables300 mm and a separate tray; crossing only at right angles
Medium voltage power cables and fire survival cables300 mm, or a fire rated barrier, with the fire survival cables on the upper tier
Control cables and extra low voltage signal or data cables150 mm, or a separate compartment of the trunking
Any power or control cable and a non electrical service such as a water, drainage or gas lineSeparation as required by the service, and never less than 300 mm, with the electrical service above the water line

Where the separation cannot be achieved, a continuous earthed metallic barrier of not less than 1.6 mm sheet steel, bonded to the earthing system at intervals not exceeding three metres, shall be provided between the categories, and the arrangement shall be approved by the Project Manager before installation. Cables of different categories shall not be drawn into the same conduit, the same compartment of a trunking or the same duct, and shall not be bunched together by a common tie.

Crossings between categories shall be made at right angles and with the greatest practicable separation at the crossing point, and shall be so arranged that the cables of the lower category pass below. Circuits fed from the normal supply and circuits fed from the generator or from an uninterruptible supply shall be kept on separate trays or in separate compartments throughout, and shall be distinguished by the identification tags so that no interchange is possible during maintenance.

10. Terminations, lugs and glands

All cables shall be terminated with double compression glands of brass with a nickel or tin finish, of the correct size for the cable, provided with an armour clamp which grips the armour over its full circumference, an earth tag, and a polyvinyl chloride or halogen free shroud where required. The gland shall be fitted to a gland plate of not less than 3 mm thickness, and where a single core cable passes through the plate the plate shall be of non magnetic material. Single compression glands may be used only for cables within a dry indoor enclosure where the Schedule of Quantities so permits.

Conductor terminations shall be made with tinned copper crimped lugs of the correct size for the conductor and the terminal, formed with a calibrated hydraulic or ratchet tool and the matching die, with the insulation removed to the exact barrel length and the conductor undamaged. Bimetallic lugs shall be used for aluminium conductors terminating on copper terminals. Soldered terminations, twisted joints and the direct entry of an unlugged stranded conductor into a terminal shall not be accepted. Where a stranded conductor is terminated in a screw clamp terminal, a ferrule or a pin type lug of the correct size shall be used.

Cable cores shall be dressed within the panel so that the bending radius is maintained, so that no strain is imposed on the terminal, and so that the cores can be traced without disturbing the adjacent cables, and they shall be secured to a cable support within the panel. The armour and the gland plate shall be bonded to the earth bar of the panel by an earth tag and a conductor of the cross section required by the earth fault current, and the continuity shall be measured. All cable entries shall be made from the position shown on the approved drawing, and all unused entries shall be blanked so that the degree of protection of the enclosure is maintained.

11. Identification and core ferruling

Every cable shall carry an identification tag of aluminium or other non ferrous metal of not less than 1.5 mm thickness, embossed or punched with the cable designation, the size and the number of cores as given in the approved cable schedule, secured by two turns of non corroding wire or by a stainless steel strap, fitted at both ends, on both sides of every wall and floor crossing, in every pull pit and at intervals not exceeding ten metres on all accessible runs. Tags on fire survival circuits shall be red and shall additionally carry the words identifying the circuit as a fire survival circuit.

Phase identification shall be provided at every termination by coloured heat shrinkable sleeves or by the core colours of the cable, consistently throughout the installation and matching the phase sequence of the busbars of the panel, and the neutral and the protective conductor shall be distinguished by their standard colours. The phase sequence and the phase identification shall be verified at both ends of every cable before it is connected.

All control, alarm and indication cores, including the spare cores, shall be ferruled at both ends with interlocking or heat shrunk ferrules bearing the wire number of the approved schematic, and the spare cores shall be ferruled, looped and terminated on spare terminals so that they are available for future use. Screens and drain wires shall be made off in a sleeve and earthed at the designated end only, with the free end insulated and labelled. A record of the core allocation of every multicore cable shall be included in the as built cable schedule.

12. Testing

Every cable shall be tested before laying, after laying and before termination, and again after termination, and the results at each stage shall be recorded on the approved format with the ambient temperature and the humidity. Insulation resistance shall be measured core to core, core to neutral, core to earth and neutral to earth with a direct current tester of not less than 1000 V for one minute, and shall be not less than the value declared by the manufacturer for the length under test, and in no case less than one megohm per kilometre corrected to the test temperature; a reading below the expected value shall be investigated before the cable is connected.

Continuity of every core, the polarity of every single pole device, the continuity and resistance of the armour and of the protective conductor from the termination to the earth bar, the phase sequence at both ends and the absence of any interchange of cores shall be verified and recorded. The earth fault loop impedance and, where fitted, the operating current and time of the residual current protective device shall be measured on every final circuit and compared with the calculated value.

A sheath integrity test shall be carried out on the outer sheath of every cable laid direct in the ground before the trench is refilled, and any damage found shall be repaired by an approved method or the affected length replaced. After energisation and loading, a thermographic survey of all terminations at the main and sub main panels shall be carried out at not less than sixty per cent of the design load, and any abnormal temperature shall be rectified by remaking the termination. All test instruments shall carry valid calibration certificates traceable to a national standard, and all tests shall be witnessed by the Project Manager on not less than three working days notice.

13. Measurement

Low tension cables shall be measured in linear metres of finished length correct to one cm, measured along the actual laid run from the centre of the gland at one end to the centre of the gland at the other end, including the vertical rise and fall and the slack left at each end, separately for each type, size and number of cores described in the Schedule of Quantities. No length shall be measured for a cable rejected on test, and no wastage shall be measured.

End terminations shall be measured by numbers of each size where separately enumerated, and shall otherwise be deemed included in the rate of the cable. Excavation, sand bedding, protective covers, warning tape, refilling and reinstatement for buried low tension cables shall be measured in linear metres of finished length of trench correct to one cm as described in Section II, and fire stopping of shaft and wall openings shall be measured in numbers of openings or in square metres of the sealed opening as stated in the Schedule of Quantities.

The rate for the cable shall be deemed to include supply, transport, handling and storage; laying in trench, duct, conduit, shaft or on trays including all clamps, cleats, ties, saddles, cushioning and dressing; identification tags, phase identification and core ferruling of all cores including the spares; the making off and earthing of screens and drain wires; all testing including insulation resistance, continuity, polarity, phase sequence, earth fault loop impedance, sheath integrity and the thermographic survey; and the as built cable schedule and route drawings.

The rate for the termination shall be deemed to include the double compression gland, the armour clamp, the earth tag and its bonding conductor to the panel earth bar, the shroud, the crimped or bimetallic lugs, the dressing of the cores within the enclosure and the blanking of unused entries. The rate for a fire survival cable shall further be deemed to include the steel supports, clamps and fixings required by its fire test certificate, the manufacturer recommended accessories, the distinctive labelling and the type test certificates. Nothing extra shall be payable on account of the design ambient temperature of 50 deg C, work at height, work in a shaft or in a confined space, or the dust laden environment.

End of Section I

Schedule of codes and standards

ReferenceTitleApplied to
IS 7098 (Part 1):1988Cross-linked polyethylene insulated PVC sheathed cables up to 1100 VXLPE cable ratings (90 °C), resistance and reactance data
IS 1554 (Part 1):1988PVC insulated (heavy duty) electric cables up to 1100 VCable ratings, resistance and reactance data
IS 694:2010PVC insulated cables for working voltages up to 1100 VFRLS wiring conductors
IS 17048:2018Fire-survival cables for fixed installationsFire-alarm / PA / pressurisation cabling
IS 8130:2013Conductors for insulated electric cables and flexible cordsConductor resistance at 20 °C; temperature coefficient for fault-level resistance correction
IS 10810cited in the specification
IS 10418cited in the specification
IS 1255cited in the specification
IS 732:2019Code of practice for electrical wiring installationsVoltage-drop limits, cable selection, protection coordination (adopts IEC 60364)
IEC 60332-3cited in the specification
IEC 61034cited in the specification
IEC 60754-2cited in the specification
IEC 60331cited in the specification
BS 6387 / BS 8434-2Fire-resistant cables — performance requirements (CWZ) / enhanced 120 minFire-survival cable grades
EN 50200cited in the specification
Prepared by
Checked by
Approved by

Results are design aids computed by designlink calc (calc.designlink.in) and must be reviewed by a qualified engineer before issue. Ground levels marked "assumed" have no survey level within reach — verify.