STP design

Step-by-step user guide — from the daily sewage flow and the plot to every tank, pump, blower, filter and press of the plant, its layout, sections, P&ID, DXF, Excel and 3D model.
Written for anyone in the office. You need a browser, your DesignLink login, the design flow (kL/day), the effluent standard the consent asks for, and the shape of the space available. The defaults reproduce the 1600 KLD MBBR reference design.
Version 1.0 · September 2026

What this tool does

It works through the standard STP calculation sheet — screen chamber, oil & grease chamber, equalisation tank, anoxic tank, MBBR (or extended aeration, SBR, MBR), tube settler, clear-water tank, sludge holding tank, flushing and soft-water tanks — then selects the electromechanical units: raw-sewage transfer pumps, aeration and mixing blowers, diffusers and media, filter-feed pumps, MGF / ACF / UF / UV, sludge recirculation and screw-press feed pumps, screw press, hypochlorite dosing, transfer / irrigation / soft-water pumps, sump pumps, instruments. Every number carries its arithmetic and its clause (CPHEEO, NCRPB, KSPCB, Metcalf & Eddy, media manufacturer). It then lays the tank block and the plant room into your plot, draws the GA with sections, the P&ID and the schedules, and builds a 3D model.

Contents

  1. Open the tool
  2. Design basis
  3. Process
  4. Hydraulic units
  5. Equipment basis
  6. Tank construction
  7. Space available
  8. Reading the results
  9. Plan, Flow, 3D, Schedules
  10. Outputs
  11. Frequently asked questions

1. Open the tool

a. calc.designlink.in → STP design (or /stp/). Sign in when asked. Type the project name.
b. Inputs on the left (six groups); on the right the tabs Results, Plan, Flow, 3D, Schedules. Results update as you type.

2. Design basis

InputWhat to enter
Daily average flowThe design capacity in kL/day (80 % of the water demand from the Water tool plus laundry / kitchen effluent).
Peak factor2.5 (NCRPB para 3.2.5) for small plants; used for the screen, O&G chamber and the equalisation peak volume.
Raw BOD / SS / COD / O&GDesign values — 350 / 300 / 650 / 75 mg/L for domestic sewage (sheet ranges 250–450, 250–400, 500–800, 50–100).
Effluent standardReuse (BOD < 5, SS < 5 — flushing / HVAC), NGT / CPCB 2019 (BOD < 10), CPCB discharge or general. It sets the BOD removed for the sludge calculation and appears on the report.
Parallel streams2 = the sample's two-stage 800 + 800 KLD (anoxic, reactors and settlers duplicated; raw-sewage pumps 2 W + 1 S per stream).

3. Process

MBBR (sample): BOD load ÷ loading rate 0.02 kg/m²·d → media area ÷ 400 m²/m³ → media volume ÷ fill 15 % → reactor volume, split into stages × streams; anoxic tank HRT 2 h.
Extended aeration: aeration volume = BOD load ÷ (F/M × MLSS); the tool checks HRT ≥ 18 h.
SBR: basins × cycles per day and the fill fraction give the basin volume (also checked against F/M); no tube settler.
MBR: high-MLSS aeration tank plus a membrane tank sized from the flux (20 LMH); no tube settler, no MGF / ACF.

Oxygen 1.4 kg per kg BOD, transfer efficiency 14 % (fine-bubble at 4–5 m) → aeration air; tube-settler surface overflow rate 35 m³/m²·d (CPHEEO Table 5.8) and media height 0.75 m.

4. Hydraulic units

Screen velocity (CPHEEO 0.6–1.2 m/s), O&G retention 6 min at peak (KSPCB 5–10), equalisation HRT 10 h or peak × 3 h whichever is larger, clear-water tank 2 h, sludge = 35 % of BOD removed + 25 % of the influent solids as inorganic, at 1 % solids and 4 days' storage. Flushing tank as hours of average flow or kL; soft-water demand (0 = no softener); UF, UV and irrigation on / off.

5. Equipment basis

Pumps and filters run 20 h/day (sheet); filtration rate 16 m/h (Metcalf & Eddy 5–25); chlorine 5 mg/L as 1 % hypochlorite solution; screw press 3 m³/h; sludge recirculation 65 % of the raw flow; blower pressure 5 m WC; mixing air 0.8 m³/h per m³ of EQT and SHT; 6 m³/h per fine-bubble diffuser.

6. Incoming sewer, levels and tank construction

a. Incoming sewer invert (m, same datum as the tank top, GL / basement floor = 0) and size (0 = sized for the peak flow). This sets the hydraulic profile: screen channel floor 100 below the invert, O&G water 150 lower (screen loss), O&G outlet → EQT with a 100 free fall. A deep sewer makes the EQT deeper than the other tanks.
b. Raw sewage pumps: auto = dry in the plant room with flooded suction, or submersible on guide rails in the EQT when the EQT floor is more than 0.6 m below the other tanks. You can force either.
c. Downstream tanks cascade by gravity: 50 mm per opening, 100 mm across an MBBR media sieve or into the tube settler; settler launders / SBR decanters drain to the clear water tank through the plant room at ≥ 1:300 (the CWT is lowered if needed). The plant room floor is 300 below the lowest tank a dry pump draws from.
d. Water depth 4.5 m, free board 0.5, walkway / top slab, wall / raft thicknesses, shallow depth 1.2 m for the O&G chamber. Maximum depth = how far the tool may deepen the tanks to fit the plot.

7. Space available and the plant room

a. Rectangle L × B, or polygon corners (irregular plots), or no constraint. The plant does not have to fill the space: the tool searches the tank-block width and plant-room width for the smallest footprint that fits.
b. Arrangement: plant room along one side, or a central plant room with the streams on both sides (auto picks the smaller). Every tank a pump draws from (EQT, SHT, settler, MBR, SBR, CWT, flushing, soft water) has a wall on the plant room, so each suction is a short flooded pipe through a sleeve.
c. Plant room: pumps stand along the tank walls in front of the tank they draw from; blowers, filters, UF, softener, screw press, dosing, MCC, stair and sump are packed in rows with 1 m aisles. The room widens (if allowed) and lengthens until everything is inside — a check turns red if it would exceed the space.
d. If the tanks do not fit, the tool deepens them up to the maximum depth, tries the other axis, then reports the shortfall in metres.

8. Reading the results

BlockWhat it tells you
ChecksScrew-press hours ≤ 20, extended-aeration HRT, tanks + plant room fit (depth used or shortfall).
Design basis / UnitsFlows, BOD load, effluent; every tank as laid out with L × W × depth and the rule behind it.
Levels / Layout / Air, sludge, power / QuantitiesLevels relative to GL; rectangle, block widths, rows; oxygen, air, sludge, connected and running kW, plant-room ventilation; RCC and excavation.
Worked stepsThe calculation sheet in words — copy into your design note.

9. Plan, sleeves, Flow, 3D, Schedules

Plan — tanks coloured by unit, plant room with pumps (blue) and blowers (light blue), filters (circles), skids, MCC, stair; sewage (brown), sludge (dark brown), air (dashed blue) and treated (blue) piping; sleeves S01, S02… (green fill = puddle flange) — hover for DN, centre line and invert.
Sleeves — wall A / B — elevation of each tank wall seen from the plant room: tanks, top water and floor levels, plant-room FFL and every sleeve at its centre-line level with its mark. Give this to the structural / site team for the inserts.
Flow — the P&ID-style schematic for the chosen process (settler + sludge recirculation, SBR decanter + sludge wasting, or MBR permeate + RAS + scour air).
3D — orbit / pan / zoom; tanks at their own water levels, pipes at their real levels, sleeves; toggle each group.
Schedules — RCC tanks (provided vs required volume, TWL, floor), electromechanical units, sleeve / puddle-flange schedule (service, wall, pipe and sleeve DN, CL, invert, type), pump piping (suction / delivery / header DN and route), ancillaries.

10. Outputs

Report — inputs, design tables, flow schematic, layout, schedules, checks, worked steps, notes, standards (Print → PDF).
Excel — a Design calculation sheet laid out like the reference sheet with the inputs in yellow and every result as a live formula, plus Tanks (area / volume formulas), Equipment, Levels, Quantities, Checks.
DXF (mm) — equipment plan, section 1-1 along the tanks, section 2-2 across plant room and reactor, the flow-schematic sheet, tank schedule, list of electromechanical units, legend and notes, on STP-* layers.

11. Frequently asked questions

The consent asks for BOD < 10. Pick the NGT / CPCB 2019 standard; the sludge quantity and the report change accordingly. Reuse for flushing still needs the UF / UV polish — leave them ticked.

My plot is narrow. Reduce the plant room width to 6 m or set the long axis manually; the tool tells you the metres missing. Deeper tanks (up to your maximum) are tried automatically.

Vendor gives different media / diffuser figures. Enter the vendor's loading rate, specific area, fill fraction and air per diffuser — the reactor and blower sizes follow.

Can I move equipment? Not yet in the tool — edit the DXF; piping is schematic. Row order follows the flow; the plant room width and stream count are inputs.

Where do pump heads come from? Raw-sewage and sludge pumps: tank height × 1.2 / 1.3 (≥ 8 m) as the sheet; transfer pumps to the building: enter from the Water tool.