DESIGNLINK CALC · calc.designlink.in
Water Supply Network Design
Step-by-step user guide — from an AutoCAD site plan to node pressures, pipe sizes, pump duty, storage, the report, the drawing and the Excel schedule.
Written for anyone in the office: no EPANET or WaterGEMS knowledge needed. You need a web browser, your DesignLink login, and a DXF of the site plan from the drawing team.
Version 1.0 · September 2026
What this tool does
You give it the site plan and tell it which lines are the water mains, where the water comes from (overhead tank, underground sump with a pump, or the municipal connection), which buildings there are and how many people use them. It then solves the whole network at peak demand — loops included, exactly like EPANET — and for every node tells you the pressure, for every pipe the flow, velocity and the size it needs, for every pump the duty point, for every building whether the top floor gets enough pressure or needs a booster, and how much storage the site needs. Everything is checked against the design code you choose (CPHEEO / NBC for India, AWWA / IPC / BS for international, DEWA / SBC / Kahramaa for the Gulf) and you get three things:
- Report — design criteria with clause numbers, sources, buildings and risers, node pressures, pipe sizing, pump curve, storage, worked example, BOQ. Print it to PDF.
- AutoCAD drawing (DXF) — the plan with pipe sizes, flows, velocities, node pressures, sources, building tags, a riser schematic per building, a summary table and a legend.
- Excel schedule — nodes, pipes, buildings, pumps, storage, BOQ. The same file can be imported back to build a project without a drawing.
How long does it take? A campus with 5–10 buildings takes about 15 minutes; most of that is typing populations and floor counts.
Contents
- Before you start — what the drawing must contain
- Open the tool and create a project
- Step 1 · Upload the DXF
- Step 2 · Pipe network layer
- Step 3 · Nodes
- Step 4 · Sources of supply
- Step 5 · Ground levels
- Step 6 · Buildings and demands
- Step 7 · Other demands
- Step 8 · Design rules
- Step 9 · Design, read the results, fix problems
- Getting the report, the drawing and the Excel
- Understanding the colours and check names
- Frequently asked questions
1. Before you start — what the drawing must contain
Ask the drawing team for a DXF (AutoCAD: File → Save As → AutoCAD 2018 DXF). The tool reads layers, so put these on their own layers:
| Item | How to draw it | Layer name (example) |
| Water mains | Polylines or lines along the pipe routes. Ends must touch at junctions (within 5 cm). Loops are fine — in fact they are good. Direction does not matter. | WATER |
| Buildings | Closed polylines (outer outline). A text inside the outline (e.g. "TOWER A") becomes the name. | BLDG (+ BLDG-TXT) |
| Ground levels | Number texts at spot levels (e.g. 244.35), contours with elevation, or 3D points. Use finished levels. | FGL |
| Everything else | Roads, boundary, tank, pump house — any layer; they are copied to the output drawing as reference. | ROAD, SITE … |
Draw the main as one polyline per road; where a branch leaves, start the branch polyline exactly on the main (use OSNAP "nearest" or "perpendicular"). A gap of a few centimetres is fixed by the "merge gaps" setting in Step 2.
2. Open the tool and create a project
a. Go to calc.designlink.in and click Water supply network design. Sign in with your DesignLink account when asked (an OTP is e-mailed to you).
b. A "New water supply project" box appears. Type the project name, choose the Standard (India, International or Gulf) and the DXF units (leave "auto"). Click Create.
The screen has three columns: Steps (left, with the layer list below it), the Plan (centre — drag to pan, wheel to zoom, "fit" to reset) and the Step editor (right). Your work is saved automatically ("Saved" appears at the top). The web address contains the project code — bookmark it to come back later.
3. Step 1 · Upload the DXF
a. Click DXF file, choose the drawing. After a few seconds the plan shows the drawing and the layer list fills in.
b. Check the notice: it shows the file name, the number of layers and the size of the site in metres. If the size is 1000× too big or small, set Drawing units (mm / m / ft) and upload again.
No drawing? Upload an Excel schedule instead (sheets Nodes, Pipes, Buildings with X, Y, GL). Download the Excel from any designed project to get the template.
4. Step 2 · Pipe network layer
a. In the Layers list click the layer with the water mains. The tool reads it and says e.g. "11 pipe(s) between 12 node(s); 2 junction(s), 4 dead end(s)".
b. Too many dead ends? Some lines don't touch. Set Merge gaps up to 0.5 m and click Re-read network from layer.
Every corner, junction and end of the lines becomes a node — a point where the tool reports the pressure.
5. Step 3 · Nodes
Long straight mains have no node in the middle, so no pressure is reported there. Type a distance (e.g. 100 m) and click Split to add nodes along the route. Click any node on the plan to give it a tag (e.g. "J-12") or type its ground level. Nodes can be deleted (the two pipes are merged).
6. Step 4 · Sources of supply
This is the most important step: water must come from somewhere with a known level or pressure.
a. Click the node on the plan where the water enters — next to the OHT, the pump house or the municipal meter. It becomes a square "source" symbol and its editor opens on the right.
b. Choose the source type:
- Overhead tank / reservoir (gravity) — type the water level above ground (staging height + water depth, e.g. 20 m).
- UG sump + pump — type how far the sump water level is below ground (e.g. 3 m). Leave the pump duty on auto: the tool finds the flow and head the pump needs so that every node meets the required pressure. Choose "given" to check an existing pump instead.
- Municipal connection — type the residual head the water board guarantees at the meter (e.g. 15 m).
You may have more than one source (e.g. a pump for the campus and a tank on the hill); the tool balances them.
7. Step 5 · Ground levels
a. Click the level layer (FGL). The tool reads every number and interpolates a ground level at each node from the nearest three levels. Click a second layer (e.g. contours) to add it.
b. Nodes marked assumed had no level within reach — type their level in the table. Levels you type are never overwritten.
Pressure is HGL minus ground level, so a wrong ground level gives a wrong pressure. Use the finished levels, not the survey.
8. Step 6 · Buildings and demands
a. Click the building outline layer. Every closed outline becomes a building, named from the text inside it, and is connected to the nearest node.
b. Click a building in the list (or on the plan) and fill in: Type (residential, hostel, hotel, hospital, office…), the quantity the type asks for (dwelling units, beds, seats, persons or floor area), Floors and floor height, number of risers. Leave LPCD blank to use the code value; type a population to override the automatic one.
c. Check the connection: click nodes on the plan to connect (a building can be split between two nodes with shares), or press Connect nearest node.
Behind the scenes: daily demand = population × LPCD; peak flow = peak factor × average (CPHEEO: 3.0 below 50 000 people). The building's peak flow is placed at its node(s).
9. Step 7 · Other demands
Add irrigation, cooling towers, swimming pools or bulk consumers at a node as a peak flow in L/s. Leave empty if none.
10. Step 8 · Design rules
Everything has a code default; change only what your project needs:
| Setting | Meaning | India default |
| Standard | Rule set with clauses used in the report | CPHEEO / NBC Pt 9 / IS 2065 |
| Head-loss law | Hazen-Williams (usual) or Darcy-Weisbach | Hazen-Williams |
| Main / riser material | Sets the C value and the available sizes | DI K9 (C 140) / GI (C 100) |
| Minimum main size | Smallest pipe the tool may choose | 80 mm |
| V min / V max | Velocity limits in mains; separate limit for risers | 0.6 – 1.8 m/s; 2.5 m/s riser |
| Residual at ground | Pressure required at each node (by storeys served) | 7 / 12 / 17 m for 1 / 2 / 3+ storeys |
| At top fixture | Pressure required at the highest tap; below it a booster is listed | 10 m (1 bar) |
| Fittings % | Minor losses as a percentage of friction loss | 15 % |
| Storage days / fractions | Daily demand × days, split UG / overhead | 1 day; 2/3 UG, 1/3 OH |
| Fire reserve kL | Added to the UG tank — take it from the fire-fighting tool | 0 |
11. Step 9 · Design, read the results, fix problems
a. Click Design network. Within a few seconds the summary line shows the peak flow, the lowest pressure and where it is, the maximum velocity and the number of failing checks. The plan colours the pipes (green = OK, amber = warning, red = check) and shows the flow arrows.
b. Read the
Results tabs below the plan:
- Pipes — size chosen, flow, velocity, head loss per km. Type a size in the Lock box to force it and design again.
- Nodes — pressure in m and bar against the required value. "PRV / zoning" means the pressure is above 60 m.
- Buildings & risers — riser size and velocity, pressure at the base and at the top fixture, and the booster (head and flow) if the top fixture is short of pressure.
- Pumps & storage — duty point (flow @ head), operating point on the curve, kW, shut-off head; UG and overhead tank volumes.
- Checks — every warning in one list.
What to do when something is red
| Symptom | Usual cause | Fix |
| Node pressure LOW and "no upsizable pipe left" | Source is too low (tank not high enough / municipal head too small) | Raise the tank level, add a pump source (auto duty), or lower the required residual in the rules |
| Pipe V > max | Locked size too small | Remove or raise the lock |
| Booster listed for a tall building | Normal above ~4 floors on a 20 m tank | Provide the booster set shown, or a terrace tank fed by a transfer pump (use the OHT kL column) |
| "not connected to any fixed-head node" | A pipe group is not joined to the source | Step 2: merge gaps, or draw the missing pipe |
| Pressure above 60 m at low nodes | Big level difference across the site | Add a PRV zone (note in report) — pressures are reported so you can place it |
12. Getting the report, the drawing and the Excel
Report — click Report (top right). It opens in a new tab. Press Print / Save PDF; choose A4 landscape.
AutoCAD DXF — click AutoCAD DXF; the file downloads. Open it in AutoCAD (any version 2018+), everything is in model space in metres, on layers W-PIPE, W-NODE, W-TEXT, W-RISER… Text height is chosen automatically from the pipe lengths.
Excel — click Excel. Sheets: Nodes, Pipes, Buildings, Pumps, Storage, BOQ, Summary.
13. Understanding the colours and check names
| Name | Meaning |
| p_low | Node pressure below the required residual |
| p_high | Node pressure above 60 m — consider a PRV / pressure zone |
| vmax | Velocity above the limit (pipe should be bigger) |
| vmin | Velocity below the minimum — water may stagnate; acceptable on small dead ends |
| noflow | Pipe carries no flow at peak (e.g. a loop that balances to zero) |
| booster | Top-fixture pressure below the minimum — booster head and flow are given |
| assumed (GL) | No survey level within reach — type it |
14. Frequently asked questions
Which flow does it use — average or peak? Pressures and sizes are for the peak hour (peak factor × average daily flow). Storage uses the daily volume.
Can I check an existing network? Yes: lock every pipe size (Pipes tab) and design; the tool then only reports pressures and velocities.
How is the pump duty found? The tool raises the pump discharge head until the worst node just meets its residual, adds the margin from the rules (2 m), and reads the flow at that head. The curve shown is a synthetic curve through that duty (133 % shut-off, 200 % run-out) — replace it with the manufacturer's curve when you order.
Internal plumbing (branch pipes, fixture units)? Not in this tool — it stops at the riser and the pressure at the top fixture. A fixture-unit tool is planned.
Fire water? Use the Fire fighting tool for the hydrant ring and pumps; put its tank volume in "Fire reserve kL" here so the UG tank includes it.
I changed the DXF. Upload again in Step 1 and re-read the network layer; sources, tags and levels you typed are kept for nodes that still exist.