USER GUIDE

Voltage drop & cable sizing

Full cascade from source to load, auto cable pick, fix-all, Excel in and out.

IS 732 · IS 1554 · CPWD

How to use it

  1. Choose the Design: Indian (IS 732 / CPWD) or International (IEC 60364). International loads the IEC preset (400 V, IEC breaker ratings, Annex G voltage-drop limits) and keeps every Indian code out of the results, report and Excel. Then pick a preset if needed — it sets the catalogue, derating and voltage-drop limits.
  2. Add feeders: From → To, kW (or A), length, phase, laying method; mark panels with 'is panel' so the tree builds.
  3. Press Autosize — cables, breakers and links are chosen; edit any cell to override, results recompute.
  4. Check the cumulative voltage drop column and the flags; fix the red rows.
  5. Save, then Report / Excel / DXF. Hand over to SLD, Short-circuit and Panel GA from the buttons.

Inputs

FieldType / defaultMeaning
PresetCPWD or IEC catalogue, ambient, grouping and VD limits
Feeder rowsfrom, to, load kW / A, PF, length m, phase, laying (air / duct / buried), runs, cable (auto)
Panelssections, incomers, fire / essential flags

What you get

OutputContent
Cable schedulesize, runs, current, derated capacity, VD %, cumulative VD, breaker
Load treeconnected / demand load per panel with diversity
Report / Excel / DXFcalculation sheet with a worked example of the largest feeder, editable workbook, cable schedule drawing

Standards applied

Good to know