USER GUIDE

Lightning protection

Risk R1 to LPS class, mesh / rolling sphere, down conductors, roof plan DXF.

IEC 62305 · IEC 61643

How to use it

  1. Enter the inputs on the left — defaults are a typical case; every field has a note.
  2. Results, checks (PASS / CHECK) and worked steps appear on the right as you type; Drawing and 3D tabs where the calculation has a layout.
  3. Save the project, then export the Report, Excel with formulas and DXF.

Inputs

FieldType / defaultMeaning
Structure
Lengthnumber (m) default 60
Widthnumber (m) default 25
Height to roof / parapetnumber (m) default 30
Highest protrusion (lift MR, OHT, mast) above roofnumber (m) default 4
Location factor Cdchoice default 0.5
Surrounded by taller objects (0.25), Surrounded by objects of same height or smaller (0.5), Isolated — no other objects nearby (1), Isolated on a hilltop or knoll (2)
Use of the structurechoice default res
Residential / apartments, Office / commercial, Hospital / nursing home (difficult evacuation), School / civic building, Hotel / hostel, Industrial / warehouse, Mall / entertainment / stadium (>1000 persons), Museum / place of worship / heritage …
Persons in the structure (nz)number default 400
Constructionchoice default rcc
RCC frame (rebar can serve as natural down conductor), Steel frame (natural down conductor), Load-bearing masonry / timber
Roofchoice default flat
Flat RCC with parapet, Metal sheet (continuous, ≥ 0.5 mm — natural air termination), Pitched tiles / sheet on purlins
Lightning density
Place (NBCS 2026 / NBC 2016 cl. 11.8 thunderstorm days → Ng = 0.1 Td)choice default delhi
Agra — Td 24, Ahmadnagar — Td 10, Ahmedabad — Td 11, Ajmer — Td 26, Akola — Td 20, Alibag — Td 12, Aligarh — Td 30, Allahabad — Td 51 …
Ground flash density Ngnumber (/km²·yr)Leave blank to use 0.1 × Td of the city; use the IMD / lightning-detection-network value when you have it
Risk factors (IEC 62305-2 Annex B/C)
Fire risk rfchoice default ord
Explosion (1), High — fire load > 800 MJ/m² (0.1), Ordinary — 400–800 MJ/m² (0.01), Low — < 400 MJ/m² (0.001), None (0)
Fire provisions rpchoice default 0.5
None (1), Extinguishers, hydrants, manual alarm, fire brigade < 10 min (0.5), Automatic sprinklers / detection + alarm (0.2)
Floor surface (touch/step) rtchoice default 1e-3
Concrete / agricultural (10⁻²), Marble, ceramic tiles (10⁻³), Gravel, carpet (10⁻⁴), Asphalt, linoleum, wood (10⁻⁵)
Touch-voltage measures PTAchoice default 1
None (1), Warning notices (0.1), Insulation of exposed down conductors / equipotential soil (0.01)
Environment of incoming lines CEchoice default 0.1
Rural (1), Suburban (0.5), Urban (0.1), Urban with buildings > 20 m (0.01)
Power linechoice default buried
Overhead LV/HV line, Buried cable, None (own DG only)
Power line length (from last pole / transformer)number (m) default 500
HV/LV transformer at the structure (CT = 0.2)yes / no default True
Telecom / data linechoice default buried
Overhead, Buried, None / fibre only
Telecom line lengthnumber (m) default 500
Coordinated SPD protection on lines (PEB)choice default auto
Auto — SPD level to match the LPS class, No SPDs, SPD for LPL III/IV (0.05), SPD for LPL II (0.02), SPD for LPL I (0.01)
Tolerable risk RTnumber (/yr) default 1e-05
Tolerable frequency of damage FT (internal systems, IEC 62305-2 : 2024)number (/yr) default 0.1indicative check of the frequency of damage F of internal systems (set by the owner; 0.1 /yr typical)
LPS design
Code editionchoice default nbcs2026
NBCS 2026 (SP 7:2026) Part D Sec 2 — IEC 62305 : 2024, NBC 2016 Part 8 Sec 2 — IS/IEC 62305 : 2010 (superseded), IEC 62305 (projects outside India)
Class of LPSchoice default auto
Auto — lowest class that brings R1 ≤ RT, I (LPL I), II (LPL II), III (LPL III), IV (LPL IV)
Air-termination methodchoice default mesh
Mesh on the roof + rods at corners / protrusions, Vertical rods (rolling sphere + protective angle), Mesh + rods at every node (belt and braces)
Air-termination rod heightnumber (m) default 1.0
Conductor materialchoice default gi
Hot-dip galvanised steel strip / rod, Copper, Aluminium (roof only)
Soil resistivity ρnumber (Ω·m) default 100
Target earth resistancenumber (Ω) default 10

What you get

OutputContent
Results, checks, worked steps, schedules; report, Excel and DXF exports.

Standards applied

Good to know