USER GUIDE

MEP supports — spans, members, anchors

Load per metre of trays, ducts and pipes → cross-member (angle / strut / channel / beam) by bending and deflection, hanger rod, anchor bolt with tension–shear interaction; trapeze, bracket or goal-post.

IS 800 · IEC 61537 · SMACNA · ETAG 001

How to use it

  1. Enter the inputs on the left — defaults are a typical case; every field has a note.
  2. Results, checks (PASS / CHECK) and worked steps appear on the right as you type; Drawing and 3D tabs where the calculation has a layout.
  3. Save the project, then export the Report, Excel with formulas.

Inputs

FieldType / defaultMeaning
Service
Servicechoice default tray
Cable tray / ladder (loaded), Sheet-metal duct, Pipe (water-filled, insulated), Custom load
Traychoice default ladder_600
ladder 300 mm — 22 kg/m, ladder 450 mm — 35 kg/m, ladder 600 mm — 48 kg/m, ladder 750 mm — 62 kg/m, ladder 900 mm — 78 kg/m, perf 150 mm — 8 kg/m, perf 300 mm — 18 kg/m, perf 450 mm — 28 kg/m …
Trays on the support (tiers)number default 2
Duct widthnumber (mm) default 800
Duct heightnumber (mm) default 400
Sheet thicknessnumber (mm) default 0.8
Insulated + claddingyes / no default True
Pipe NBchoice default 100
25 NB — 3.1 + 0.6 kg/m, 32 NB — 4.1 + 1.0 kg/m, 40 NB — 4.8 + 1.3 kg/m, 50 NB — 6.2 + 2.2 kg/m, 65 NB — 8.6 + 3.6 kg/m, 80 NB — 10.3 + 5.0 kg/m, 100 NB — 14.5 + 8.7 kg/m, 125 NB — 18.0 + 13.5 kg/m …
Pipes on the supportnumber default 2
Insulatedyes / no default True
Load per metre runnumber (kg/m) default 60
Extra allowance (person / future)number (kg) default 90IEC 61537 / SMACNA: a 90 kg point load for a person on trays, or future services
Support
Arrangementchoice default trapeze
Trapeze on two hanger rods, Wall / column cantilever bracket, Floor stand / goal-post
Support spacing (along the run)number (m) default 1.5
Cross-member length (between rods / cantilever)number (mm) default 900
Cross-memberchoice default auto
Auto — lightest that passes, ISA 40x40x5 — 3.0 kg/m, Z 1.55 cm³, ISA 50x50x6 — 4.5 kg/m, Z 3.0 cm³, ISA 65x65x6 — 5.8 kg/m, Z 5.1 cm³, ISA 75x75x6 — 6.8 kg/m, Z 7.0 cm³, ISA 100x100x8 — 12.1 kg/m, Z 17.0 cm³, Strut 41x21x2.5 — 1.3 kg/m, Z 0.9 cm³, Strut 41x41x2.5 — 2.3 kg/m, Z 3.0 cm³ …
Steel design methodchoice default lsm
IS 800:2007 limit state — γm0 1.10, load factor 1.5 (NBCS Part C Sec 6A), Allowable stress 0.66 fy — IS 800:1984 (withdrawn) / AISC ASD, legacy
Load factor γf (dead + imposed)number default 1.5IS 800:2007 Table 4: 1.5 for DL + IL
Steel yieldnumber (MPa) default 250
Deflection limit L/number default 240
Hanger rodchoice default auto
Auto, M10 (4.6), M12, M16, M20
Anchors per rod / bracketnumber default 1
Concrete gradechoice default M25
M20 (× 0.85), M25, M30 (× 1.1)
Safety factor on anchor loadsnumber default 1.5

What you get

OutputContent
Results, checks, worked steps, schedules; report, Excel and DXF exports.

Standards applied

Good to know