USER GUIDE

UPS & battery sizing

Module count for N / N+1 / 2N, battery Ah, charger, room heat and H₂ venting.

IEEE 485 · IEC 62040

How to use it

  1. Enter the inputs on the left — defaults are a typical case; every field has a note.
  2. Results, checks (PASS / CHECK) and worked steps appear on the right as you type; Drawing and 3D tabs where the calculation has a layout.
  3. Save the project, then export the Report, Excel with formulas.

Inputs

FieldType / defaultMeaning
Load
Critical loadnumber (kW) default 80
Load power factornumber default 0.9
Future growthnumber (%) default 20
UPS output rated power factornumber default 0.9modern double-conversion UPS: 0.9–1.0 (kW = kVA × pf)
Max loading of UPSnumber (%) default 80
Redundancychoice default n1
N (single), N+1 (parallel), 2N (dual bus)
Modules in parallel for N (N+1 adds one)number default 2
Battery
Backup timenumber (min) default 30
Battery typechoice default vrla
VRLA (lead-acid, 12 V blocks), Li-ion (LFP)
DC bus nominal voltagenumber (V) default 384typical 384 / 480 / 528 V for 3-phase UPS (32 / 40 / 44 blocks of 12 V)
End-of-discharge voltage per cellnumber (V) default 1.75
Inverter efficiencynumber default 0.95
Ageing factornumber default 1.25IEEE 485: 1.25 (replace at 80 % capacity)
Temperature factornumber default 1.01.0 at 25 °C; 1.1 at 20 °C; 1.2 at 15 °C (VRLA)
Design marginnumber default 1.1
Peukert exponent (blank = by type)numberVRLA at high rates ≈ 1.3; Li-ion ≈ 1.05
Block capacity (0 = auto)number (Ah) default 0
Installation
UPS overall efficiencynumber default 0.94
Input power factornumber default 0.99
Input voltage (3-phase)number (V) default 415
Recharge to 90 % withinnumber (h) default 10
UPS outputchoice default 3
Three-phase (4-pole CB, NBCS 10.3.2 e), Single-phase 230 V (double-pole CB)
NBCS 2026 D2 10.3.2 / 10.3.4 provisions
Isolation transformer on the UPS output (10.3.2 a, optional)yes / no default False
Dedicated UPS neutral earth pits, interconnected below soil (10.3.2 b)yes / no default True
UPS room ventilated / air-conditioned (10.3.2 d)yes / no default True
Battery space well ventilated (10.3.4 d)yes / no default True
Acid / alkali-resistant battery-room floor (10.3.4 e)yes / no default True
UPS-fed circuits marked at the DBs (10.3.4 a)yes / no default True

What you get

OutputContent
Results, checks, worked steps, schedules; report, Excel and DXF exports.

Standards applied

Good to know