All calculators
Plumbing / PHE · Live

STP design

Screen and oil-and-grease chambers, equalisation, anoxic + MBBR (or extended aeration, SBR, MBR), tube settler, clear-water and sludge tanks, flushing and soft-water tanks; pumps, blowers, diffusers, media, MGF / ACF / UF / UV, dosing, screw press, by the CPHEEO / NCRPB method with worked steps; layout in the plot, GA DXF with sections, P&ID, Excel with live formulas and 3D.

CPHEEO Manual on Sewerage and Sewage Treatment (2013) Part A ch. 5NBCS 2026 (SP 7:2026) Part E Sec 2NCRPB Functional Plan — Water & SewerageKSPCB STP design guidelinesCPCB / NGT 2019 (as amended)Metcalf & Eddy, Wastewater Engineering (5th ed.)
What goes in, what comes out

You enter

  • Flow (KLD), influent quality, effluent standard
  • Process choice, plot shape
  • Equipment options

You get

  • Unit sizes, equipment list, blowers, pumps
  • GA DXF, P&ID, Excel, 3D
  • Report

What it does

Process trainMBBR, ASP, SBR or MBR with the standard pre- and post-treatment.
Worked stepsEvery tank sized with the formula, the loading rate and the clause.
Blowers and diffusersOxygen demand, SOTE, blower duty and diffuser count.
Layout in the plotTanks and equipment room inside your boundary with sections.
P&IDProcess and instrumentation sheet with the equipment tags.
Live ExcelDesign sheet with formulas, GA DXF, report, 3D.

Checks it performs

PASS / CHECKEffluent BOD / TSS ≤ CPCB 2019 limits
PASS / CHECKMBBR fill fraction ≤ 70 %
PASS / CHECKTube-settler surface loading within CPHEEO
PASS / CHECKBlower capacity ≥ oxygen demand with margin
PASS / CHECKLayout fits the plot with access

Sample report

Also searched as

STP design calculation; sewage treatment plant design MBBR; STP capacity calculation for building; STP P&ID and layout; SBR STP design; MBR sewage treatment plant sizing. The same calculation, the same clauses — one tool for plumbing / phe design under the Indian codes (NBC, IS, CPWD) or the international ones (IEC, NFPA, ASHRAE, EN).

Standards applied

ReferenceTitleUsed for
CPHEEO Manual on Sewerage and Sewage Treatment (2013) Part A ch. 5Screens, grit, settling and biological treatment design parametersScreen velocity 0.6–1.2 m/s, anoxic detention, secondary settling SOR (Table 5.8), F/M and MLSS ranges
NBCS 2026 (SP 7:2026) Part E Sec 2National Building Construction Standards — Drainage and sanitationSanitary fixtures by occupancy (Tables 1–17), DFU, stacks, vents, building drains, rainwater pipes (Table 25)
NCRPB Functional Plan — Water & SewerageNational Capital Region Planning Board — sewerage normsPeak factor 2.5 (para 3.2.5)
KSPCB STP design guidelinesKarnataka State Pollution Control Board — STP design and O&MO&G chamber retention 5–10 min
CPCB / NGT 2019 (as amended)Standards for sewage treatment plant effluentTreated effluent BOD / SS / COD limits for reuse and discharge
Metcalf & Eddy, Wastewater Engineering (5th ed.)Treatment and resource recoveryFiltration rates, SBR cycle design, MBR flux, oxygen requirement
H. H. Bengtson, MBBR Wastewater Treatment ProcessMoving-bed biofilm reactor designSurface area loading rate (BLR) for media sizing
IS 3370:2021 (Parts 1–4)Concrete structures for retaining aqueous liquidsRCC water tank walls / slabs, minimum thickness and crack control (quantities are indicative)
IS 18797:2024Packaged sewage treatment plants — specificationPackaged / prefabricated STP where a septic tank is not permitted (NBCS 2026 Part E Sec 2)

Frequently asked

How do I use the STP design calculator?

Open the tool, change the pre-filled example to your project, read the results, checks and worked steps as you type, then export the report, Excel and DXF.

Which codes and standards does the stp design follow?

It applies CPHEEO Manual on Sewerage and Sewage Treatment (2013) Part A ch. 5, NBCS 2026 (SP 7:2026) Part E Sec 2, NCRPB Functional Plan — Water & Sewerage, KSPCB STP design guidelines, CPCB / NGT 2019 (as amended), Metcalf & Eddy, Wastewater Engineering (5th ed.) and others. Every result line shows the formula and the clause it comes from, and the report lists the standards applied.

What does it check?

Every run is marked PASS or CHECK against: Effluent BOD / TSS ≤ CPCB 2019 limits; MBBR fill fraction ≤ 70 %; Tube-settler surface loading within CPHEEO; Blower capacity ≥ oxygen demand with margin; Layout fits the plot with access.

Is the calculator free to use?

Yes — running the calculation, reading the results, checks and clauses is free. One design credit unlocks the report, Excel and DXF exports for 30 days; the first design is free on sign-in.

Can I see a sample report before I use it?

Yes, a complete sample report for this tool is published at https://calc.designlink.in/samples/stp/ — inputs, results with basis, checks, worked example, drawing and the standards list.

Is this the same as a STP design calculation?

Yes. People also call it a sewage treatment plant design MBBR, a STP capacity calculation for building, a STP P&ID and layout. It covers the same calculation under plumbing / phe design, with the Indian and international code regimes selectable.

Does it work with AutoCAD or ZWCAD?

Yes — with the free DesignLink CAD plugin the tool reads rooms, layers and selections from the open drawing and places its DXF output straight back into the plan; without the plugin you upload a DXF and download the result.

Related plumbing / phe calculators