The front end of the electrical chain: type or import the room schedule (or pull it from the building model), pick each room's occupancy, and the tool derives lighting, socket, AC, HVAC and equipment loads from the regime's densities, packs them into circuits under the CPWD / IEC rules, balances the boards, sums the floor and main panels with diversity and hands the feeder schedule to Power Distribution Design.

NBCS 2026 (SP 7:2026) Part D Sec 2NBC 2016 Part 8 Sec 2IS 732:2019CPWD General Specifications for Electrical Works Part I (Internal) 2023ECBC 2017 (BEE)IS 3043:2018
What goes in, what comes out

You enter

    You get

      What it does

      Regime densitiesECSBC 2024 (ECBC 2017 option) / ASHRAE 90.1 lighting W/m², NBC raw-power VA/m² or socket points, AC kind per occupancy — all overridable per room.
      DB schedulesLighting circuits ≤ 800 W / 10 points, 2 × 16 A per circuit, dedicated AC circuits; MCB and wire per circuit; R-Y-B balanced; ways with spare; incomer and RCCB.
      Panel treeBoards → floor panels → main LT panel with demand factors per category and per level; lifts, pumps, chillers as plant loads; transformer and DG size.
      Feeds PDDOne click creates the Power Distribution Design project with every feeder — cables, fault levels and SLD continue there; lighting watts come from the lux project when linked.

      Checks it performs

      PASS / CHECKCircuit limits (W, points, sockets per circuit)
      PASS / CHECKPhase unbalance ≤ 15 %
      PASS / CHECKBoard ways with spare
      PASS / CHECKDemand ≤ incomer rating

      Sample report

      How to use it

      1. Set the basis: regime (Indian / International), system voltage and pf, boards scheme (combined LPDB or LDB + PDB per floor and zone), panel tree, demand factors, and the plant loads at the panels (lifts, pumps, chillers).
      2. Add rooms — type them, import the Excel, pull them from a Building-model project (areas and names) or from a Lighting project (designed lighting watts and luminaire counts).
      3. Check the room-wise loads: every auto value (light W, points, sockets, AC units, equipment) can be typed over; set the board tag where you want rooms grouped by hand.
      4. Read the DB schedules (circuits, phases, MCBs, wires, incomer, RCCB, unbalance) and the panel tree with demand, kVA and the transformer / DG size.
      5. Export the report and the Excel (rooms, one sheet per board, panels, feeders), then Send to PDD for the cable sizing, fault levels and SLD.

      What you enter

      • Rooms — floor, zone, name, occupancy type, area
      • Overrides — light W / points, 6 A and 16 A points, AC kind / units, equipment kW, board, panel
      • Basis — regime, voltage, pf, boards and panel scheme, ways and spare, demand factors, plant loads

      What you get

      • Loads — connected by category per room and floor, W/m²
      • DB schedules — circuits with description, points, W, phase, MCB, wire; incomer, RCCB, ways, unbalance
      • Panels — floor / main demand with diversity, kVA, transformer and DG size; feeder schedule for PDD

      Also searched as

      electrical load calculation for building; connected load and demand load calculator; DB schedule maker; load estimation as per NBC 2016; lighting and power load calculation per sq m; electrical load estimation excel alternative. The same calculation, the same clauses — one tool for electrical design under the Indian codes (NBC, IS, CPWD) or the international ones (IEC, NFPA, ASHRAE, EN).

      Standards applied

      ReferenceTitleUsed for
      NBCS 2026 (SP 7:2026) Part D Sec 2National Building Construction Standards — Electrical and allied installationsLoad assessment and diversity, circuits, cables (4-core), earthing, lightning protection, standby supply for fire & life-safety loads
      NBC 2016 Part 8 Sec 2National Building Code — Electrical and allied installations (load assessment)Load assessment per occupancy, demand factors, sub-circuits, DBs
      IS 732:2019Code of practice for electrical wiring installationsVoltage-drop limits, cable selection, protection coordination (adopts IEC 60364)
      CPWD General Specifications for Electrical Works Part I (Internal) 2023Internal electrical installationsSub-circuit limits (800 W / 10 points), 16 A socket circuits, wiring sizes, DB construction
      ECBC 2017 (BEE)Energy Conservation Building Code — superseded by ECSBC 2024; still enforced where a State has not yet notified ECSBC 2024Envelope U / SHGC and lighting power density (India option)
      IS 3043:2018Code of practice for earthingEarth bus, strip sizing, earthing of panels (future earthing tool)
      IEC 60364-1Low-voltage electrical installations — fundamental principles, assessment of general characteristicsMaximum demand and diversity
      IEC 60364-5-52:2009Low-voltage electrical installations — Selection and erection of wiring systemsCurrent-carrying capacity, derating (temperature, grouping, installation method), voltage drop ≤ 3–5 %
      BS 7671:2018+A2Requirements for Electrical Installations (IET Wiring Regulations)Radial / ring circuit arrangements, diversity (Appendix 15 / on-site guide)
      ASHRAE 90.1-2019Energy Standard for BuildingsLighting power density by space type

      Frequently asked

      How do I use the Load estimation & DB schedules calculator?

      Set the basis: regime (Indian / International), system voltage and pf, boards scheme (combined LPDB or LDB + PDB per floor and zone), panel tree, demand factors, and the plant loads at the panels (lifts, pumps, chillers). Add rooms — type them, import the Excel, pull them from a Building-model project (areas and names) or from a Lighting project (designed lighting watts and luminaire counts). Check the room-wise loads: every auto value (light W, points, sockets, AC units, equipment) can be typed over; set the board tag where you want rooms grouped by hand.

      Which codes and standards does the load estimation & db schedules follow?

      It applies NBCS 2026 (SP 7:2026) Part D Sec 2, NBC 2016 Part 8 Sec 2, IS 732:2019, CPWD General Specifications for Electrical Works Part I (Internal) 2023, ECBC 2017 (BEE), IS 3043:2018 and others. Every result line shows the formula and the clause it comes from, and the report lists the standards applied.

      What does it check?

      Every run is marked PASS or CHECK against: Circuit limits (W, points, sockets per circuit); Phase unbalance ≤ 15 %; Board ways with spare; Demand ≤ incomer rating.

      Is the calculator free to use?

      Yes — running the calculation, reading the results, checks and clauses is free. One design credit unlocks the report, Excel and DXF exports for 30 days; the first design is free on sign-in.

      Can I see a sample report before I use it?

      Yes, a complete sample report for this tool is published at https://calc.designlink.in/samples/load/ — inputs, results with basis, checks, worked example, drawing and the standards list.

      Is this the same as a electrical load calculation for building?

      Yes. People also call it a connected load and demand load calculator, a DB schedule maker, a load estimation as per NBC 2016. It covers the same calculation under electrical design, with the Indian and international code regimes selectable.